Dormakaba ED100 Installation Instructions Manual

Dormakaba ED100 Installation Instructions Manual

Automatic swing door operators, installation in surface applied (narrow) header
Hide thumbs Also See for ED100:
Table of Contents

Advertisement

ED100/ED250
Automatic Swing Door Operators
Installation in Surface Applied (Narrow) Header
Installation Instructions
DL4615-006 – 01-2020
| EN |

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the ED100 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Dormakaba ED100

  • Page 1 ED100/ED250 Automatic Swing Door Operators Installation in Surface Applied (Narrow) Header Installation Instructions DL4615-006 – 01-2020 | EN |...
  • Page 2: Table Of Contents

    ED100/ED250 operator component view 12.5 Double egress arm configurations Accessory kits, axle extension kits 12.6 Double door center hung arm ED250 and ED100 configured for full configurations Header installation energy accessory kit ED100 low energy accessory kit 13.1 Installation preparation Arm configurations 13.2...
  • Page 3 ED100/ED250 SA Installation Instructions Table of Contents Arm with track mount installation Install header cover 15.1 Arm with track installation 28.1 Install header cover Install door signage 15.2 Splined arm and track assemblies 15.3 Splined arm and track hardware 29.1...
  • Page 4: General Information

    Chapter 1 1 General information 1.1 Installation Instructions This manual provides installation instructions for ED100/ED250 automatic swing door operators used in single door and double door surface applied header installations. 1.2 Manual storage This document must be kept in a secure place, and accessible for reference as required.
  • Page 5: Product Description

    2.6 Hardware as shipped. exterior swing doors. 2.6.1 Single swing door. The ED250 or ED100 operator is installed in a surface 1. Box containing surface mount header assembly for mount header at customer site. The header must be one ED100/ED250 operator. Included inside header: installed on an interior building surface.
  • Page 6: Safety Information

    Chapter 3 3 Safety information 3.1 Safety instructions. This document contains important instructions for installation of the ED100/ED250 swing door operators. WARNING Review these instructions thoroughly prior to installation, and follow them carefully during installation, Hand pinch point and crushing hazards at door commissioning, troubleshooting and maintenance.
  • Page 7: Ed100/Ed250 Product Overview

    Header assembly with cover Fig. 4.1.6 Header without operator ED100/ED250 4" x 6" header Header cover Cover screws Program switch panel mounting Fig. 4.1.2 Header with ED100/ED250 operator surface Jamb brackets 4" x 6" header track Splined spindle ED100/ED250 operator...
  • Page 8: Ed100/Ed250 Pair Swing Doors

    ED100/ED250 SA Installation Instructions Chapter 4 ED100/ED250 pair swing doors Fig. 4.2.1 Double header Double header Header cover Cover screws Program switch panel Hole for drive axle Header track Hole for spring Fig. 4.2.2 Double header without operators tension adjustment Fig.
  • Page 9: Ed100/Ed250 Operator Component View

    ED100/ED250 SA Installation Instructions Chapter 4 ED100/ED250 operator component view Fig. 4.3.1 ED100/ED250 component view 1 Fig. 4.3.2 ED100/ED250 component view 2 Power switch 120 VAC terminals Housing unit Splined spindle Operator (motor, gear, spring Spring tension adjustment, closing force...
  • Page 10: Accessory Kits, Axle Extension Kits

    ED100/ED250 SA Installation Instructions Chapter 5 5 Accessory kits, axle extension kits ED250 and ED100 configured for full energy accessory kit Fig. 5.1.1 Decal kit, low energy Fig. 5.1.2 Decals, full energy DD0586-010 SAFETY INFORMATION Automatic Swinging Doors These minimum safety checks,...
  • Page 11: Ed100 Low Energy Accessory Kit

    ED100/ED250 SA Installation Instructions Chapter 5 ED100 low energy accessory kit Fig. 5.2.1 Decal kit, low energy Fig. 5.2.2 Push arm screw kit DD0586-010 SAFETY INFORMATION Low Energy Swinging DD0758-010 Doors AUTOMATIC These minimum safety checks, in addition to those in the Owner’s Manual, should be...
  • Page 12: Arm Configurations

    ED100/ED250 SA Installation Instructions Chapter 5 Arm configurations Fig. 5.3.1 Splined push arm assembly, Fig.5.3.4 Splined push arm assembly, 225 mm 500 mm Drive arm Adjustment shaft tube, 225 mm 2.2 Adjustment shaft, 225 mm Shoe Axle extension Adjustment shaft tube, 450 mm 5.2 Adjustment shaft,...
  • Page 13: Double Door Ed100/Ed250 Operator Connection Cables

    ED100/ED250 SA Installation Instructions Chapter 5 Double door ED100/ED250 operator connection cables Fig. 5.5.1 Communication cable Fig. 5.5.2 115 VAC power cable Communication cable DX3485-010, 250 mm, 9 7./8" DX3485-020, 1030 mm, 40 1/2" DX3485-030, 2030 mm, 80" RJ45 plug...
  • Page 14: Technical Data

    ED100/ED250 SA Installation Instructions Chapter 6 6 Technical data ED100/ED250 Technical data 6.1.1 Required operating conditions 6.1.4 Outputs Maximum wire size Ambient temperature 5 to 122 °F 16 AWG Connector plug 1/16” Suitable for dry Relative air humidity: screw size...
  • Page 15: Operating Specifications

    8" minimum to 19 11/16" Note 1 push arm Full energy / low energy • F.E.: ED100 configured for full energy • L.E.: ED100 configured for low energy Note 2 Speeds automatically limited depending on door weight, set during learn cycle.
  • Page 16: Recommended Tools And Torque Chart

    ED100/ED250 SA Installation Instructions Chapter 7 7 Recommended tools and torque chart Recommended tools Fig. 7.1.1 Recommended tools T-handle hex key, 5 Hex keys, 2.5 mm, 3 mm, 6 mm Screwdriver, flat blade Door pressure gauge, 0 to 35 ft - lbf...
  • Page 17: Operational Mode Overview

    Parameter hS, power assist function support for door in closed position. Low energy product 8.2.1 ANSI/BHMA 156.19. ED100 operator is configured to meet requirements of a low energy application per ANSI/BHMA A156.19, U.S. Standard for Power Assist and Low Energy Power Operated Doors.
  • Page 18: User Interface

    ED100/ED250 SA Installation Instructions Chapter 9 9 User interface Overview Fig. 9.1.1 Operator keypad and display 9.1.1 Operator user interfaces. 2 digit display 1. 4 button keypad and 2 digit display. 4 button keypad • 4 button keypad; to select, input and adjust door parameter values.
  • Page 19: Program Switch Panel, Optional Key Switch Panels

    ED100/ED250 SA Installation Instructions Chapter 9 Program switch panel, optional key switch panels Fig. 9.3.1 Program switch panel 9.3.1 Program switch control modes. • Auto, door opens automatically when Program switch one of the activators is actuated or panel...
  • Page 20: System Accessories

    Manual release switch ED100/ED250 header 10.2 System accessories 10.2.1 Overview 10.2.6 Activators ED100 / ED250 operators are normally Typical activators: used with system accessories available from 1. Motion detectors dormakaba or other manufacturers. 2. Infrared safety sensors 10.2.2 Accessory electrical installation.
  • Page 21 ED100/ED250 SA Installation Instructions Chapter 10 10.3 ED100/ED250 terminal board interfaces. Fig. 10.3.1 Terminal board electrical connections Green LED (Para. 9.4) Night- Activation inputs Yellow LED (Para. 9.4) Interior Exterior bank Safety sensors input Red LED (Para. 9.4) DCW bus...
  • Page 22: Ed100/Ed250 Door Signage

    ED100/ED250 SA Installation Instructions Chapter 10 10 ED100/ED250 door signage 10.1 Full energy operator 10.1.1 Overview Fig. 10.1.1 One decal, approach, non-approach Signage and warnings are specified in ANSI /BHMA A156.10, American National Standard for Power DO NOT Operated Pedestrian Doors, paragraph 11.
  • Page 23: Door Signage, Full Energy Single Swing Door

    ED100/ED250 SA Installation Instructions Chapter 11 11.3 Door signage, full energy single swing door Fig. 11.3.1 One decal, one way traffic Fig. 11.3.2 One decal, two way traffic Approach Non-approach Non-swing side Swing side DO NOT AUTOMATIC CAUTION ENTER...
  • Page 24: Door Signage, Full Energy Double Swing Doors

    ED100/ED250 SA Installation Instructions Chapter 11 11.5 Door signage, full energy double swing doors Fig. 11.5.1 One way traffic, approach side Fig. 11.5.2 One way traffic, non-approach side DO NOT DO NOT ENTER ENTER dormakaba dormakaba AUTOMATIC AUTOMATIC AUTOMATIC...
  • Page 25 ED100/ED250 SA Installation Instructions Chapter 11 Fig. 11.5.7 Double egress, RH, one way traffic, interior Fig. 11.5.8 Double egress, RH, one way traffic, exterior Approach side Swing side Swing side Approach side DO NOT DO NOT ENTER ENTER dormakaba...
  • Page 26: Door Signage, Low Energy Double Swing Doors

    ED100/ED250 SA Installation Instructions Chapter 11 11.6 Door signage, low energy double swing doors Fig. 11.6.1 Knowing act, SA header side Fig. 11.6.2 Knowing act, hinge side AUTOMATIC AUTOMATIC AUTOMATIC AUTOMATIC CAUTION CAUTION CAUTION CAUTION DOOR DOOR DOOR DOOR...
  • Page 27: Safety Label, Automatic Swing Doors

    The appropriate and the hardware should by an ED100 or ED250 operator configured for the low signage should be present. be in good condition. energy mode. 7. Have door inspected by an 6.
  • Page 28: 12.1 Ed100/Ed250 Sa Arm Configurations

    ED100/ED250 SA Installation Instructions Chapter 12 12 ED100/ED250 SA arm configurations 12.1 Single swing door right hand arm configurations Fig. 12.1.1 RH pull Pull arm Track Fig. 12.1.2 RH deep pull Track Pull arm with CPD lever Fig. 12.1.3...
  • Page 29: 12.2 Single Swing Door Left Hand Arm

    ED100/ED250 SA Installation Instructions Chapter 12 Fig. 12.1.5 RH deep push Deep push arm Door stop (optional) 12.2 Single swing door left hand arm configurations Fig. 12.2.1 LH pull Pull arm Track Fig. 12.2.2 LH deep pull Track Pull arm with CPD lever Fig.
  • Page 30: Single Swing Door Center Hung Door Arm

    ED100/ED250 SA Installation Instructions Chapter 12 Fig. 12.2.4 LH push Push arm Door stop (optional) Fig. 12.2.5 LH deep push Deep push arm Door stop (optional) 12.3 Single swing door center hung door arm configurations Fig. 12.3.1 Center hung door, RH push arm Fig.
  • Page 31 ED100/ED250 SA Installation Instructions Chapter 12 Fig. 12.3.5 Center hung door, LH pull arm Fig. 12.3.3 Center hung door, RH pull arm Track Pull arm with CPD lever Bottom pivot assembly (by others) Fig. 12.3.6 Center hung door, pull as push RH Fig.
  • Page 32: Double Door Arm Configurations

    ED100/ED250 SA Installation Instructions Chapter 12 12.4 Double door arm configurations Fig. 12.4.1 Double door pull Pull arm Track Fig. 12.4.2 Double door deep pull Track Pull arm with CPD lever Fig. 12.4.3 Double door pull as a push...
  • Page 33: Double Egress Arm Configurations

    ED100/ED250 SA Installation Instructions Chapter 12 12.5 Double egress arm configurations Fig. 12.5.1 Double egress LH Track Pull arm with CPD lever Push arm Fig. 12.5.2 Double egress RH Track Pull arm with CPD lever Push arm ED100/ED250 DL4615-006...
  • Page 34: 12.6 Double Door Center Hung Arm Configurations

    ED100/ED250 SA Installation Instructions Chapter 12 12.6 Double door center hung arm configurations Fig. 12.6.1 Center hung door, double door pull Track Pull arm with CPD lever Bottom pivot assembly (by others) Top pivot assembly (by others) not shown Fig.
  • Page 35: 13 Header Installation

    13.1.3 Accessories WARNING 1. Verify accessories planned for or in place for the door. ED100 / ED250 header assembly should be Chapter 10, accessories, list typical accessory types installed by trained and knowledgeable for ED100 /ED250 operators. installers experienced in installation and commissioning of automatic door closers.
  • Page 36: 13.3 Remove Mounting Plate From

    1. Remove 115 Vac plug (5) from its receptacle (6). 13.3.2 Remove mounting plate from operator. 1. Loosen all eight captive ED100 / ED250 M6 socket head cap screws (SHCS) using a 5 mm hex T-handle. TIPS AND RECOMMENDATIONS Insure all eight fasteners are free of the mounting plate.
  • Page 37: Single Header Installation

    ED100/ED250 SA Installation Instructions Chapter 13 13.4 Single header installation 13.4.1 Single header installation preparation. Fig. 13.4.1 Door frame width 1. Door frame installed. Header width 2. Confirm header width. • Header width equals door frame width plus three inches.
  • Page 38: Install Program Switch Panel In Header

    ED100/ED250 SA Installation Instructions Chapter 13 Fig. 13.4.4 Header located on door frame Screws in bottom slide channel Screws in top V-groove (located on stud centerlines) Program switch panel (may be in different location) Low voltage wiring 115 VAC wiring (may...
  • Page 39: Double Header Installation

    ED100/ED250 SA Installation Instructions Chapter 13 13.6 Double header installation 13.6.1 Double header installation preparation. Fig. 13.6.1 Header and door frame width 1. Door frame installed. 2. Confirm header width. Header width • Header width equals door frame width plus three Door frame width inches.
  • Page 40 ED100/ED250 SA Installation Instructions Chapter 13 Fig. 13.6.3 Header located on door frame/wall Screws in bottom Low voltage and 115 slide channel VAC wiring (may be Screws in top in different location) V-groove (located on Program switch stud centerlines)
  • Page 41 ED100/ED250 SA Installation Instructions Chapter 13 13.7 SA narrow header (4 x 6") – push arm template Fig. 13.7.1 Standard push arm template 0 to 8 3/4” Reveal depth 90° 20 1/16” [510] Header width = door width + 3”...
  • Page 42 ED100/ED250 SA Installation Instructions Chapter 13 13.8 SA narrow header (4 x 6") – deep push arm installation template Fig. 13.8.1 Deep push arm template 90° Reveal depth 26 5/16” [667] Header width = door width + 3” [76.2] 5 7/8”...
  • Page 43 ED100/ED250 SA Installation Instructions Chapter 13 13.9 SA narrow header (4 x 6") – pull arm template Fig. 13.9.1 Deep pull arm template 5 7/8” 1 1/2” 1 1/2” [38] [149] [38] 2” [48] 3/4” [19] 17 3/4” 7”...
  • Page 44: Sa Narrow Header (4 X 6") - Deep Pull Arm Template

    ED100/ED250 SA Installation Instructions Chapter 13 13.10 SA narrow header (4 x 6") – deep pull arm template Fig. 13.10.1 Deep pull arm template 1 1/2” 5 7/8” [38] [147] 3 7/8” [99] 1 1/8” 7” 17 3/4” [178]...
  • Page 45: Sa Narrow Header (4 X 6") - Center Hung Door, Push Arm Template

    ED100/ED250 SA Installation Instructions Chapter 13 13.11 SA narrow header (4 x 6") – center hung door, push arm template Fig. 13.11.1 Push arm template 2 3/4” [70] 16” [413] 90° 5 7/8” 1 1/2” [149] [37] 1/2” [13] 1 1/2”...
  • Page 46 ED100/ED250 SA Installation Instructions Chapter 13 13.12 Offset pivot door, surface applied header, push arm template Fig. 13.12.1 Offset pivot door, surface applied header, push arm template 2 3/4” [70] 5 3/4” 1 1/2” [38] [147] 2 3/8” [59] 7 7/8”...
  • Page 47 ED100/ED250 SA Installation Instructions Blank page This page left intentionally blank. ED100/ED250 DL4615-006 01-2020...
  • Page 48 ED100/ED250 SA Installation Instructions Blank page This page left intentionally blank. ED100/ED250 DL4615-006 01-2020...
  • Page 49: Ed100/Ed250 Operator Installation

    ED100/ED250 SA Installation Instructions Chapter 14 14 ED100/ED250 operator installation 14.1 Single header mounting plate installation Fig. 14.1.1 Header with header tracks Header track Operator axle hole Program switch panel Fig. 14.1.2 Mounting plate Mounting plate 2 (12) 1/4 x 20 UNC hole...
  • Page 50: Double Header Mounting Plate Installation

    ED100/ED250 SA Installation Instructions Chapter 14 14.2 Double header mounting plate installation Fig. 14.2.1 Double header with header tracks Axle centerline Program switch Header track panel Fig. 14.2.2 Double header with mounting plates installed Guide pin Third guide pin Fig.
  • Page 51 Fig. 14.3.1 Mounting plate power connection side WARNING 115 Vac terminal block Routing and connection of 115 Vac Ground terminal wiring to ED100 / ED250 must be Terminal block screw performed by a qualified person! torque label Preferred 115 Vac wiring entry point WARNING 115 Vac branch circuit disconnect or Fig.
  • Page 52 ED100/ED250 SA Installation Instructions Chapter 14 14.4 Remove protective film strips from operator Fig. 14.4.1 Operator heat conductive pads Heat conductive pad 14.4.1 Remove protective film strips. Fig. 14.4.2 Protective film strip 1. Remove two protective film strips from Protective film strip operator heat conductive pads.
  • Page 53 ED100/ED250 SA Installation Instructions Chapter 14 14.5 Install ED100/ED250 operator on mounting plate in header Fig. 14.5.1 Header with mounting plate installed Guide pin 115 Vac plug and cable to mounting plate 115 Vac terminal block M6 SHCS mounting hole Fig.
  • Page 54: 14.3 Customer 115 Vac Connection To

    ED100/ED250 SA Installation Instructions Chapter 14 Fig. 14.5.5 Header with operator installed 14.6 Double header ED100/ED250 operator installation Fig. 14.6.1 Double header with operators installed Fig. 14.6.2 115 Vac power cable installed on 14.6.1 Install operators on mounting operator with 115 Vac customer plates.
  • Page 55: Connect Cables To Ed100/Ed250 Operator

    ED100/ED250 SA Installation Instructions Chapter 14 14.7 Connect cables to ED100/ED250 operator Fig. 14.7.1 Header with ED100/ED250 operator Program switch panel Header for program switch cable COM 1 service connector Fig. 14.7.2 Cable installation on operator Fig. 14.7.3 Program switch panel...
  • Page 56: Arm With Track Mount Installation

    ED100/ED250 SA Installation Instructions Chapter 15 15 Arm with track mount installation 15.1 Arm with track installation NOTICE Reference Para. 12.2 (single door) and Para. 12.3 (double door) installation templates. 15.2 Splined arm and track assemblies Fig. 15.2.1 Splined arm with CPD lever and Fig.
  • Page 57: Slide Shoe Assembly

    ED100/ED250 SA Installation Instructions Chapter 15 15.4 Slide shoe assembly 15.4.1 Install pivot pin into slide shoe. Fig. 15.4.1 Slide shoe and pivot pin 1. Insert pivot pin into slide shoe. Slide shoe Pivot pin 2. Install spring clip into pivot pin slot.
  • Page 58: Fasten Track Assembly To Door

    ED100/ED250 SA Installation Instructions Chapter 15 15.5 Fasten track assembly to door 15.5.1 Mount track assembly on door. Fig. 15.5.1 Track assembly Track CAUTION Fixing piece Slide shoe Insure track hardware is Bumper assembled for hand of door. Wood screw 1.
  • Page 59: Arm Assembly

    ED100/ED250 SA Installation Instructions Chapter 15 15.6 Arm assembly Fig. 15.6.1 Arm assembly 15.7 Arm assembly with CPD lever 15.7.1 Arm with CPD lever assembly. Fig. 15.7.1 Slotted Fig. 15.7.2 M6 x 10 spring SHCS M6 x 10 SHCS...
  • Page 60: Mount Drive Arm To Operator

    ED100/ED250 SA Installation Instructions Chapter 15 15.8 Mount drive arm to operator 15.8.1 Mount drive arm to operator. Fig. 15.8.1 Mount drive arm to operator at 12 degrees WARNING 12° Use caution when working in proximity of door and drive arm!.
  • Page 61 ED100/ED250 SA Installation Instructions Chapter 15 Fig. 15.8.6 Fastening drive arm to pivot pin 15.8.2 Attach drive arm to pivot pin. 1. Use 6 mm T handle hex key to rotate pivot pin M8 socket head into drive arm and tighten.
  • Page 62: Push Arm Installation

    ED100/ED250 SA Installation Instructions Chapter 16 16 Push arm installation 16.1 Push arm installation templates NOTICE Reference Chapter 13 for installation templates. Fig. 16.1.1 Push arm assemblies Standard push arm, reveal depths 0 - 8" maximum Deep push arm reveal depths 8 - 12"...
  • Page 63: Install Push Arm Assembly

    ED100/ED250 SA Installation Instructions Chapter 16 16.3 Install push arm assembly Fig. 16.3.1 Drive arm installation, 16.3.1 Mount drive arm to operator. LH push Splined drive arm WARNING Axle extension Use caution when working in proximity of door M8 x 1.25 x 40 SHCS and push arm!.
  • Page 64 ED100/ED250 SA Installation Instructions Chapter 16 Fig. 16.3.5 Arm assemblies attached to door and ED50 16.3.4 Connect adjustment arm to drive arm. 1. Loosen the two adjustment M6 x 10 mm flanged button head screws (Fig. 16.3.5). 1. Using square, position adjustment arm assembly at 90⁰...
  • Page 65: Measure Reveal Depth, Door Width

    30 mm (1 1/8"). Parameter rd setting = 0 (Reveal of 30 mm - 30 mm). 17.3 rd parameter values 17.3.1 ED100/ED250 reveal depths, rd parameter 17.3.2 ED250 additional reveal depths, rd parameter Reveal measurement Reveal measurement Reveal measurement...
  • Page 66: Door Width Parameter Tb

    Door width is set in increments of 100 mm (4"), Measured width of 1000 mm (39.4") = Tb value of "10". ED100: [700 - 1219 mm] 28" - 48" ED250: [700- 1219 mm] 28" -48" 17.5 Record door width measurement, Tb value...
  • Page 67: Braking Circuit Plug

    ED100/ED250 SA Installation Instructions Chapter 19 18 Braking circuit plug 18.1 Braking circuit plug position Fig. 18.1.1 Braking circuit socket and plug, plug factory installed in pull installation location Braking circuit plug Braking circuit 3 pin socket User interface 18.1.1 Braking circuit plug.
  • Page 68: Operator Spring Tension

    ED100/ED250 SA Installation Instructions Chapter 18 19 Operator spring tension 19.1 Set operator spring tension 19.1.2 Operator spring tension function. Fig. 19.1.1 Spring tension adjustment 1. Spring tension sets closing force on door. 2. Required spring tension is based on door width.
  • Page 69: Power Fail Closing Speed

    20.1.2 Setting door closing speed upon power failure. 1. Turn ED100 / ED250 power switch OFF. 2. Manually open door to 90° angle and let it close. 3. If door closes in less than 5 seconds, turn...
  • Page 70: Parameters

    Operator firmware version is displayed during first Program switch, commissioning. Reference Chapter 22. 3 position • dormakaba handheld can be used to check operator firmware version and to perform firmware updates. • Reference Appendix C, dormakaba handheld, or dormakaba handheld manual.
  • Page 71 ED100/ED250 SA Installation Instructions Chapter 21 21.1.5 Configuration parameters Parameter Driving parameter Description Description Installation type Cycle counter, number displayed * 10000 Reveal depth Delete error log Door width Reset service interval display (yellow LED) Door type Factory setting level (Fact Setup button) 21.1.6 Driving parameters...
  • Page 72 100 mm (4"), "10" = 1000 mm (39.4"). Factory setting = bold. ED250 7 to 16 Installation type • ED100: [711 - 1219 mm] 28" - 48" • ED250: [711- 1219 mm] 28" - 48" Pull • Arm with track (Fig. 21.1.4).
  • Page 73: Single Door First Commissioning

    ED100/ED250 SA Installation Instructions Chapter 22 22 Single door first commissioning 22.1 First commissioning Fig. 22.1.1 Program switch Conditions prior to commissioning. Program switch, 3 position 1. Header with operator is installed. 2. Standard push arm or arm with track is installed.
  • Page 74: Set Configuration Parameters

    ED100/ED250 SA Installation Instructions Chapter 22 22.2 Set configuration parameters 22.2.1 Set parameter AS, installation type. Fig. 22.2.1 4 button keypad, 2 digit display Step 1 Press and hold PRG > 3 s to enter Four button Press program mode, AS parameter keypad displayed.
  • Page 75: Key Switch Option; Set Parameter Ps, Program Switch Type

    ED100/ED250 SA Installation Instructions Chapter 22 22.2.3 Set parameter Tb, door width. Fig. 22.2.2 4 button keypad, 2 digit display Step 13 Four button Press Scroll to Tb parameter. keypad < 3s Quit Two digit display > 3s Reset >...
  • Page 76: Perform Learning Cycle

    ED100/ED250 SA Installation Instructions Chapter 22 22.4 Perform learning cycle CAUTION Step 1 Secure motion range of door. Learning cycle must be performed while Step 2 Set program switch to CLOSE position. motor is cold! Rotating "o" and a "0" indicates CAUTION operator learning cycle is required.
  • Page 77: Double Door First Commissioning

    ED100/ED250 SA Installation Instructions Chapter 23 23 Double door first commissioning 23.1 Separately commission active and inactive doors 23.1.1 Commission active door first. 1. Refer to Para.22.1 and commission active door. 23.1.2 Commission inactive door. 1. Refer to Para.22.1 and commission inactive door.
  • Page 78: Connect Communication Cable Between Operators

    ED100/ED250 SA Installation Instructions Chapter 23 23.2.2 Inactive door, set parameter dL. 1. Set program switch to CLOSE. 2. Set parameter dL (door type) for inactive door. Step 1 Step 5 Press and hold PRG > 3 s to enter...
  • Page 79: Connect Accessory Wiring

    ED100/ED250 SA Installation Instructions Chapters 24 and 25 24 Connect accessory wiring 24.1 Connect accessory wiring 24.1.1 Connect accessory wiring. 1. Terminate all accessory wiring at ED100/ED250 terminal board. TIPS AND RECOMMENDATIONS 2. Secure all accessory wiring. • Reference Chapter 10, System Accessories.
  • Page 80: Install Push Arm Door Stop

    ED100/ED250 SA Installation Instructions Chapter 27 27 Install push arm door stop 27.1 Install push arm bumper stop (optional assembly) Fig. 27.1.1 Bumper stop assembly TIPS AND RECOMMENDATIONS 1/2" thick base plate Contact local dormakaba USA, DC4633-002 Inc. distributor for bumper stop (4) 5.1...
  • Page 81: 28 Install Header Cover

    ED100/ED250 SA Installation Instructions Chapters 28 and 29 28 Install header cover 28.1 Install header cover 28.1.1 Install header cover. 1. Install header cover on header and CAUTION secure with supplied flat head screws. Before installing cover, check Note: Headers with pull arms shown as an header assembly: example.
  • Page 82: 30 Ansi/Bhma Standards

    ED100/ED250 SA Installation Instructions Chapter 30 30 ANSI/BHMA standards 30.1 A156.10 Power operated pedestrian doors The following table references portions of content from ANSI/BHMA A156.10. Refer to the standard, available through ANSI or BHMA for additional information. Standard material reprinted with BHMA permission.
  • Page 83 ED100/ED250 SA Installation Instructions Chapter 30 30.2 A156.19 Low energy power operated doors The following table references portions of content from ANSI/BHMA A156.19. Refer to the standard, available through ANSI or BHMA for additional information. Standard material reprinted with BHMA permission.
  • Page 84 ED100/ED250 SA Installation Instructions Chapter 30 30.2.2 A156.19, Table I: Minimum opening and closing times. "W" door weight, pounds "D" door width, inches 3.0 s 3.5 s 3.5 s 3.0 s 3.0 s 3.5 s 4.0 s 4.0 s 4.5 s...
  • Page 85 ED100/ED250 SA Installation Instructions Blank page This page left intentionally blank. ED100/ED250 DL4615-006 01-2020...
  • Page 86: 31 Upgrade Cards

    31 Upgrade cards 31.1 Upgrade cards 31.2 Container module 31.1.1 Upgrade card installation. 31.2.1 Container module. dormakaba upgrade cards can be used to expand the range of • The first upgrade card installed becomes functions of ED100/ED250 operators. the container module.
  • Page 87: Installing Upgrade Cards

    ED100/ED250 SA Installation Instructions Chapter 30 31.3 Installing upgrade cards 31.3.3 Installing additional upgrade cards. 31.3.1 Set program switch to CLOSE. Upgrade card slot 1. Remove container Second upgrade module from upgrade Set program switch to Close. card card slot.
  • Page 88: Safety Label, Automatic Swing Doors

    ED100/ED250 SA Installation Instructions Chapter 32 32 Maintenance Fig. 32.1.2 Safety information labels 32.1 Safety label, automatic swing SAFETY INFORMATION SAFETY INFORMATION Automatic Swinging Doors Low Energy Swinging doors Doors These minimum safety checks, in addition to those in the 32.1.1 Automatic swinging door safety information...
  • Page 89: Ed100/Ed250 Environment And Cleaning

    Chapter 32 32.3 ED100/ED250 environment and cleaning 32.3.1 ED100/ED250 environmental requirements. Table 32.3.1 Operator environmental requirements. ED100/ED250 header assembly is designed to operate Ambient temperature 5 to 122 °F on an interior building surface under the specifications shown in Table 32.3.1.
  • Page 90: Pull Arm Maintenance

    ED100/ED250 SA Installation Instructions Chapter 32 32.5 Pull arm maintenance Fig. 32.5.1 Pull arm with track assembly, track mounting screws Fig. 32.5.3 Program switch 32.5.1 Track mounting screws. 1. Set program switch to CLOSE. 2. Remove track end caps 3.
  • Page 91: 32.5.1 Arm Fasteners - Torque Requirements

    ED100/ED250 SA Installation Instructions Chapter 32 32.5.1 Arm fasteners – torque requirements 32.5.1.1 Check drive arm M8 SHCS torque. Fig. 32.5.1.1 Spindle M8 SHCS 1. Set program switch to CLOSE. 2. Remove cap over M8 SHCS. 3. Check torque.
  • Page 92: Push Arm Maintenance

    ED100/ED250 SA Installation Instructions Chapter 32 32.6 Push arm maintenance Fig. 32.6.1 Push arm assembly Fig. 32.6.4 Program switch 32.6.1 Push arm maintenance. WARNING Set program switch to CLOSE before performing maintenance! 1. Adjustment arm. • Check for wear or damage.
  • Page 93 ED100/ED250 SA Installation Instructions Chapter 32 32.6.1 Push arm – M8 SHCS torque requirements 32.6.1.1 Drive arm M8 SHCS torque. Fig. 32.6.1 Push arm M8 SHCS 1. Remove spindle cap. 2. Check tightness of M8 SHCS. 3. Replace spindle cap.
  • Page 94: Appendix A - Driving Parameters

    ED100/ED250 SA Installation Instructions Appendix A Appendix A - Driving Parameters Driving parameters – detail A.1.1 Driving parameters detail. Value Factory Parameter Units Description range setting Opening speed, automatic mode 1. Opening speed refers to automatic mode, speed can be adjusted using this parameter.
  • Page 95 ED100/ED250 SA Installation Instructions Appendix A A.1.1 Driving parameters detail. Value Factory Parameter Units Description range setting Safety sensor test Safety sensor parameter ST must be set to sensors used and if they are active-high or active-low. See E 04 safety sensor test error, Appendix B.4.
  • Page 96 ED100/ED250 SA Installation Instructions Appendix A A.1.1 Driving parameters detail. Value Factory Parameter Units Description range setting Power reserve module SVP-PR 12 test Test off 1. SVP-PR 12 power reserve module test is performed once every 24 hours, or 10 minutes after AC power has been turned on.
  • Page 97 ED100/ED250 SA Installation Instructions Appendix A A.1.1 Driving parameters detail. Value Factory Parameter Units Description range setting Push & Go 1. Parameter is activated. 2. Automatic opening of door is started when door is manually moved 4° out of the 0 - 1 closed position.
  • Page 98 (v1.9). 1. Status relay activated when door is opened further than opening angle parameter OA, set during learning cycle. 2. Parameter OA value can only be changed using dormakaba handheld or by performing another learning cycle. Locking device output configuration;...
  • Page 99 ED100/ED250 SA Installation Instructions Appendix A A.1.1 Driving parameters detail. Value Factory Parameter Units Description range setting Factory setting level Parameter SL is used to determine what data will be reset during factory setting process. Standard factory settings •...
  • Page 100 ED100/ED250 SA Installation Instructions Appendix A A.1.1 Driving parameters detail. Value Factory Parameter Units Description range setting Power assist function (v1.7) 1. Force setting for Power assist function. 2. Power assist function only available with hd parameter = 1, manual mode.
  • Page 101 COM 1 configuration interface Interface programmed for communication with dormakaba handheld. 0 - 1 Interface programmed for use with dormakaba TMS Soft control software. Back check when door opened manually 1. Angle after which door is braked when manually opened.
  • Page 102 ED100/ED250 SA Installation Instructions Appendix A A.1.1 Driving parameters detail. Value Factory Parameter Units Description range setting Deactivation of drive; X6, 4 and 4a, trigger type (v1.7) NC contact, drive function is deactivated when NC contact is open. 0 - 1 NO contact, drive function is deactivated when NO contact is closed.
  • Page 103: Appendix B - Troubleshooting

    E 0 through E 9. B.1.3 User information display. 2. The latest error message is always stored in error User interface display, or dormakaba handheld displays: memory location E 0: • Information ln codes • As soon as another error occurs, the existing error Error message E codes •...
  • Page 104: Red Led Status Codes

    ED100/ED250 SA Installation instructions Appendix B Red LED status codes B.2.1 Red LED status codes. Red LED status Display Description Control unit has detected error, Steady flashing emergency mode activated. On steady ln 11 Hold-open device triggered. Flashing 2 times E 02 Locking device error.
  • Page 105: Troubleshooting Chart, "Ln" Codes

    ED100/ED250 SA Installation instructions Appendix B Troubleshooting chart, "ln" codes B.3.1 Troubleshooting chart, information messages. Display Description Troubleshooting information messages Sustained operation on a door with an obstruction can result in damage to drive. 1. Object or person obstructing door movement.
  • Page 106: Troubleshooting Chart, "E" Code

    4. Check for activation of the test at the safety sensors. EEPROM error • Internal memory check could 1. Using dormakaba handheld, reload current firmware to Flashing not be completed. reinitialize system. E 12 12 x •...
  • Page 107 ED100/ED250 SA Installation instructions Appendix B B.4.1 Troubleshooting chart, "E" codes (continued). • Description Display Red LED Troubleshooting error codes Overcurrent detection 1. Motor is consuming too much power, check for any external Flashing • Motor is consuming more causes.
  • Page 108: Appendix C - Dormakaba Handheld

    ED100/ED250 SA Installation Instructions Appendix C Appendix C - dormakaba handheld dormakaba handheld C.1.2 Handheld key functions. 1. OFF ON, switches Handheld on or off. Fig. C.1.1 dormakaba handheld 2. Function keys F1 - F3, trigger functions shown in Off/On key bottom line of display (e.g., "RPT"...
  • Page 109: Configuration Parameters

    ED100/ED250 SA Installation Instructions Appendix C NOTICE Parameters and detail may change depending on firmware version. Configuration parameters C.2.1 Configuration parameters Parameter and Parameter and Description / Selections Description / Selections default default Pull arm Signal ignored once Off*...
  • Page 110: Driving Parameters

    ED100/ED250 SA Installation Instructions Appendix C C.2.1 Configuration parameters Parameter and Description / Selections default Parameter and Description / Selections Manual mode on. default Manual mode Manual mode disabled. NO contact; night- bank function Normal* Power assist triggered while contact...
  • Page 111: Special Functions (Upgrade Cards)

    ED100/ED250 SA Installation Instructions Appendix C Special functions (Upgrade cards) C.4.1 Special functions (upgrade cards) Parameter and Parameter and Description / Selection Description / Selection default default • locked: not available locked Upgrade • unlocked: available, not active card status unlocked •...
  • Page 112: Diagnostics

    ED100/ED250 SA Installation Instructions Appendix C Diagnostics C.5.1 Diagnostics Parameter name Description Setting Parameter name Description Setting FW vers BM Displays firmware (FW) x.x y y (e.g.,0190 Wartungs x x y y (month, version of basic module v 1.9.0)
  • Page 113: New Dormakaba Handheld; Language

    ED100/ED250 SA Installation Instructions Appendix C New dormakaba handheld; language change to English 5. Press to select Sprachen (Fig. 18.6.6). ENTER C.6.1 New dormakaba handheld; Fig. C.6.1 language change. dormakaba handheld Fig. C.6.7 Sprachauswahl (Language If German language is displayed on screen...
  • Page 114: Dormakaba Handheld; Firmware Update

    ED100/ED250 SA Installation Instructions Appendix C dormakaba handheld; firmware update C.7.1 Firmware update procedure CAUTION For all firmware changes, set program switch to CLOSE and allow door to close completely before any updates are made! Fig. C.7.1 Handheld power on sequence...
  • Page 115 ED100/ED250 SA Installation Instructions Appendix C Fig. C.7.5 Select Firmware upload Fig. C.7.4 Select UpDoLd ENTER button F2 button Up/down arrows DOWN/UPLOAD Connected with: Download data ED100_US Upload file FW-Version: 02.30 Firmware upload Revision: Door Again UpDoLd Door 4. Press F2 to select UpDoLd.
  • Page 116: Appendix D - Header Hole Preparation

    ED100/ED250 SA Installation instructions Appendix D Appendix D - Header hole preparation D.1.1 Header, no preparation Fig. D1.1.1 Header with no hole preparation Fig. D1.1.2 Header and cover side view 6” 4” 5” D.1.2 Single LH header Fig. D1.2.1 LH single header 1 1/2"...
  • Page 117 ED100/ED250 SA Installation instructions Appendix D Fig. D1.4.2 RH single header top view 2x Ø 17/64” [432] thru 3 3/16” Ø 1/2” [12.7] x 82° [81] 1/2” [12.7] 1/2” [12.7] Fig. D1.4.3 RH single header bottom view 2 x Ø 17/64” [6.7] thru Ø...
  • Page 118: Appendix E - Wiring Diagrams

    ED100/ED250 SA Installation instructions Appendix E Appendix E - Wiring diagrams E1.1 DX4604-21C Key Switch Panel with RJ45 connector Fig. E1.1 Key switch panel DX4604-21C Fig. E1.2 Key switch panel wiring diagram 3 B A 1 57 57a 15 17...
  • Page 119: E2.1 Dx4604-11C Key Switch Panel

    ED100/ED250 SA Installation instructions Appendix E E2.1 DX4604-11C Key Switch Panel Fig. E2.1 Key switch panel DX4604-11C Fig. E.2.2 Key switch panel wiring diagram 3 B A 1 57 57a 15 17 13 3 Swing Approach side side Feedback...
  • Page 120 USA, Inc. 1 Dorma Drive, Drawer AC Reamstown, PA 17567 T: 717-336-3881 www.dormakaba.com F: 717-336-2106...

This manual is also suitable for:

Ed250

Table of Contents

Save PDF