operations occur correctly. If possible, using a P.C. or laptop computer loaded with Reydisp Evolution software,
check the current and voltage waveforms and relay operations. For phase-earth faults, check that correct
tripping as per scheme is obtained i.e. either single pole tripping or three pole tripping with the associated control
operations.

6 Putting Into Service

Remove the external test connections and heavy duty test plugs
Check that the current and voltage transformer are wired for normal operation
Check that all a.c. and d.c. supply links and fuses are inserted
Check that the earth links are inserted
Check that all the relay settings are as recommended.
Test and reset the LED indication display
Replace the relay cover
Insert the trip link
©2011 Siemens Protection Devices Limited
7SG164 Ohmega 400 Series Commissioning
Chapter 9 Page 6 of 6

Advertisement

Table of Contents
loading

This manual is also suitable for:

7sg16 ohmega 402-607sg1641 ohmega 402 60

Table of Contents