8. Before Operation

8.1

Checks Before Initial Start-up

Caution
Make sure that the circuit breaker on the power supply panel of the installation is switched off.
Attach the power wire securely.
Introducing power with a missing N-phase or with a mistaken N-phase will break the equipment.
After the installation, check the following before switching on the circuit breaker:
1. The position of the switches that require an initial setting
2. Power supply wiring and transmission wiring
3. Pipe sizes and pipe insulation
4. Additional refrigerant charge
5. Insulation test of the main power circuit
6. Installation date
Installation Manual
Make sure that switches are set according to your application needs before turning the
power supply on.
Use a designated power supply and transmission wiring and make sure that it has been
carried out according to the instructions described in this manual, according to the wiring
diagrams and according to local and national regulations.
Make sure that correct pipe sizes are installed and that the insulation work is properly
executed.
The amount of refrigerant to be added to the unit should be written on the included "Added
Refrigerant" plate and attached to the rear side of the front cover.
Using a megatester for 500V, check that the insulation resistance of 2M Ω or more is attained
by applying a voltage of 500V DC between power terminals and earth. Never use the
megatester for the transmission wiring.
Be sure to keep record of the installation date on the sticker on the electric box lid according
to EN60335-2-40.