Summary of Contents for Laser Dollhouse Designs Straight Staircase and Landing rail

  • Page 1 Straight Staircase and Landing rail Assembly Instruction By Laser Dollhouse Designs...
  • Page 2 PARTS Note: Read through instructions prior to gluing parts to understand the assembly process. STAIRCASE ASSEMBLY Staircase-1 Staircase handrail-1 Newel post-2 Treads-12 Landing tread-1 Balusters - 13 LANDING RAIL ASSEMBLY Balusters- 15 Upper/lower rail- 2 Newel Post- 3...
  • Page 3 Staircase Assembly **Decide which side you want to have the handrails, we will be installing the 12 smaller treads with cutouts on the side you want to have the handrail based on house and build. For this example in Figure 1 we are installing the rails to the left. So holes will be to the left for the string, if going right side railing just turn the tread holes to opposite side.** Step 1.
  • Page 4 Step 2. Install top tread making sure it is aligned to the rear of staircase, see figure 3. Step 3. Install the 13 balusters into the hole of each tread, figure 4. Locate the handrails notice that it has a slot in the bottom for the securing of the balusters, fig.
  • Page 5 Step 5. Using two fingers and light pressure pinch each baluster into the handrail. Do not glue until you have all seated and the bottom aligns to lower Newel post. Figure 5. Install top newel post aligning to the front of the handrail, fig.6 Glue assembly and staircase is completed, figure 7.
  • Page 6 Landing Railing Assembly NOTE: If you DO NOT have good access to your stairs location then use a stock card and make a template of your stair landing where you plan to install railing. Using the template you will assemble the rails outside of the house. Glue inside house once assembled.
  • Page 7 Landing Railing Assembly Step 3. Using markings, mark and then using a sharp blade trim two railings to size, figure 3 Step 4. Using the short side of the landing opening lay out desired number of Balusters, below in figure 4 we have three spaced.
  • Page 8 Landing Railing Assembly Step 5. Glue first Newel post to floor, figure 6. (If using template DO NOT glue newel post in, move to next step) Step 6. Glue rail to the first Newel post, figure 7. Post should be top handrail centered to Newel post top flush post point.
  • Page 9 Landing Railing Assembly Step 7. Install 2 Newel post. Follow the same process for completing remaining rails. Figure 9. If you used a template once all rails are together with newel post glue rails into house. Figure 8 Figure 9...