SLAVE UPS Setting Procedure

!
NOTE
1. Before the UPS setting, install the metal cover plates for the UPS.
2. Keep door closed except when the "MAINT" button located on the SW1
CAUTION
1. Supply the AC input and the Bypass input voltage to the UPS.
Initialization will start. Under initializing, the UPS will automatically:
Turn on contactor CB1;
-
-
Initialize converter operation;
Initialize inverter operation;
-
After initialization, LCD screen should appear.
(Refer to the G2020 series service manual, 5-1 Start-up Procedure for details.)
2. Press the "MAINT" button located on the SW1 PCB (DPAU-81*).
Maintenance screen will appear.
3. Press the "SETUP" tab on the Maintenance screen, and then press the "INPUT PORT" button.
4. Press the "IN4" button, and select item "9: ANOTHER BUS. SYNC." by pressing
"
" key then press "OK" button.
1. As the "IN4" default setting, it may be "POWER DEMAND".
2. Before making a change of the "IN4" setting, make sure that the POWER DEMAND
ATTENTION
5. Press the "CLOSE" button, and confirm that "9: ANOTHER BUS. SYNC." is lay out.
6. Press the "MAINTENANCE" tab, and then press the "MAIN MENU" button for completion of SLAVE UPS
SETTING.
12
The setting for MASTER UPS is unnecessary.
PCB (DPAU-81*) is pressed.
function is defunct.
(Contact Toshiba International Corporation, if POWER DEMAND function is under service.)
G2020 TOSHIBA SYNC KIT Installation Manual - 200153-001