Download Print this page

WE-EF ETC120-FS LED Installation And Maintenance Instructions Manual page 5

Inground luminaire

Advertisement

Phase One
Blockout Installation Procedure
(during earth or masonry work)
1) Ensure a suitable recess is provided to accommo-
date installation blockout/mounting ring assembly
B/M.
2) Set installation blockout/mounting ring assembly
B/M in position and ensure that:
a) Arrow R on mounting ring M is pointed towards
the object to be illuminated (wall, tree, column).
b) Mounting ring M
appropriate gap.
c) Mains supply cable(s) O
connect sealable junction box J with cable E from
luminaire.
3) During ongoing earth and/or masonry works,
Ensure that installation blockout/mounting ring
assembly B/M is not damaged and has maintained
its original shape. If necessary use a cover plate.
Phase Two
Luminaire Installation and Electrical Connection
4) Switch off mains electrical supply.
5) Check that rating shown on luminaire label conforms
with mains electrical supply.
6) Terminate cable E from luminaire housing A and
mains supply cable O (for individual wiring) or
branch cable (for through wiring) in sealable junc-
tion box J – to connect cable(s). Follow the seal-
able junction box termination instruction included
F. If the
in the packaging.
7)
and sealable junction box J inside installation
blockout/mounting ring assembly B/M.
For wallwash illumination only
Ensure the arrow indicated on the sticker is facing
D.
the illuminated surface (Fig. IV)
8) Loosen countersunk screws C (do not turn out).
Insert mounting lever L between head of counter-
sunk screws C and cover lens. Place luminaire
housing A into installation blockout/mounting ring
assembly B/M (Fig. III) while aligning holes D on
mounting ring M.
Warning: When luminaire is placed inside installa-
tion blockout B, ensure there is no stress on seal-
able junction box J or electric cables (Fig. V).
9) Tighten countersunk screws C 'hand-tight'.
4
D. Set cables

Advertisement

loading

This manual is also suitable for:

Evc120-fs led