Figure 25. Securing the control panel to a stand-alone system
Preparing the 9009-41A, 9009-42A, or 9223-42H system for operation after removing
and replacing the control panel
To prepare the system for operation after removing and replacing a control panel, complete the steps in
this procedure.
Procedure
1. Ensure that you have the electrostatic discharge (ESD) wrist strap on and that the ESD clip is plugged
into a ground jack or connected to an unpainted metal surface. If not, do so now.
2. Replace the service access cover.
For a rack-mounted system, complete the following steps. Refer to Figure 26 on page 28.
a. Slide the cover (A) onto the system unit.
b. Close the release latch (B) by pushing it in the direction shown.
Control panel and control panel display for the 9009-41A, 9009-42A, or 9223-42H 27