STANDARD OPERATING PROCEDURE
String Inverter Installation - Zeverlution Series
Version 1.2 Effective date 02/08/2017
SOP Title:
Version:
Effective Date:
DOCUMENT CONTROL
Version no.
Date
1.0
08/05/17
1.1
03/07/17
1.2
02/08/17

Table of Contents

PURPOSE ..................................................................................................................................... 2
SCOPE .......................................................................................................................................... 2
SYMBOLS USED IN THIS DOCUMENT ............................................................................................ 2
GENERAL GUIDELINES .................................................................................................................. 2
BEHAVIOURAL .................................................................................................................................. 2
SAFETY ............................................................................................................................................. 2
INSTALLATION PROCEDURE ......................................................................................................... 3
String Design Guidelines ................................................................................................................... 3
5.1.1
String Layout Without Optimisers ....................................................................................................... 3
5.1.2
String Layout with Optimisers .............................................................................................................. 3
5.1.3
Shading ................................................................................................................................................. 3
5.1.4
Maximum String Voltage...................................................................................................................... 4
String Inverter Installation ................................................................................................................ 4
5.2.1
Zeversolar Zeverlution 2000s ............................................................................................................... 4
5.2.2
Zeversolar Zeverlution 4000 ................................................................................................................ 4
5.2.3
Wall Mounting ..................................................................................................................................... 5
Wiring .............................................................................................................................................. 6
5.3.1
DC Wiring ............................................................................................................................................. 6
5.3.2
TS4-R-O Optimiser installation ............................................................................................................. 9
5.3.3
AC Wiring ........................................................................................................................................... 10
SYSTEM COMMISSIONING ......................................................................................................... 11
Commissioning Tests ...................................................................................................................... 11
Grid Protection Settings ................................................................................................................. 11
6.2.1
Adjusting grid protection settings using the inverter display ............................................................ 11
Connecting the inverter to the Internet ........................................................................................... 12
6.3.1
Connecting the inverter to the internet using WIFI ........................................................................... 13
6.3.2
Connecting the inverter to the internet using Ethernet .................................................................... 15
String Inverter Installation - Zeverlution Series
SOP1103-PV-v1.2
02/08/2017
Significant Changes
Draft
Issued
Monitoring setup revised
Author
Timm Brehm
Timm Brehm
T Heine
Page 1 of 15
Reviewer
TH, AF, ME, KW
TH, AF, ME, KW
TB

Advertisement

Table of Contents
loading

Summary of Contents for Zeversolar Zeverlution Series

  • Page 1: Table Of Contents

    STANDARD OPERATING PROCEDURE String Inverter Installation – Zeverlution Series Version 1.2 Effective date 02/08/2017 String Inverter Installation – Zeverlution Series SOP Title: SOP1103-PV-v1.2 Version: Effective Date: 02/08/2017 DOCUMENT CONTROL Version no. Date Significant Changes Author Reviewer 08/05/17 Draft Timm Brehm...
  • Page 2: Purpose

    MPPT inverters for residential solarZero and solarClassic systems. SCOPE This document applies to single-phase installations with Zeversolar string inverters and covers the mechanical and electrical part of the inverter installation instruction. The focus of this SOP lies on the physical installation of Zeverlution 2000s and Zeverlution 4000 inverters and any associated switch gear, DC and AC wiring.
  • Page 3: Installation Procedure

    STANDARD OPERATING PROCEDURE String Inverter Installation – Zeverlution Series Version 1.2 Effective date 02/08/2017 INSTALLATION PROCEDURE String Design Guidelines To ensure efficient operation and compliance with the regulations, string design options are limited. As per AS/NZS 5033 section 2.1.6, PV modules that are in the same string must have the same tilt and azimuth angle within a tolerance of ±5°.
  • Page 4: Maximum String Voltage

    STANDARD OPERATING PROCEDURE String Inverter Installation – Zeverlution Series Version 1.2 Effective date 02/08/2017 5.1.4 Maximum String Voltage The maximum length of a single string is dictated by the string voltage, taking temperature coefficients and the local ambient temperatures into account. For all solarcity installation zones, the maximum number of panels in a single string of 60-cell modules with a rated output at STC of less than or equal to 300 Watts, is ten (10).
  • Page 5: Wall Mounting

    STANDARD OPERATING PROCEDURE String Inverter Installation – Zeverlution Series Version 1.2 Effective date 02/08/2017 Model Zeverlution 4000 Convertible power 4650W Max input voltage 600V MPP voltage range 100V - 520V Min DC start voltage Max DC input current 11A / 11A AC Output The inverter has an AC screw terminal block for connecting the AC cabling.
  • Page 6: Wiring

    STANDARD OPERATING PROCEDURE String Inverter Installation – Zeverlution Series Version 1.2 Effective date 02/08/2017 Clearances Heat must be able to dissipate from the inverter through the heatsink on the back. It is important to consider the recommended clearances. The below table is for a single inverter only.
  • Page 7 STANDARD OPERATING PROCEDURE String Inverter Installation – Zeverlution Series Version 1.2 Effective date 02/08/2017 Any DC cabling must be adequately mechanically protected and must be run in HD Solar conduit. Where it is exposed to direct sunlight, HD conduit, marked with the letter T, is to be used. For any internal cable runs (e.g.
  • Page 8 STANDARD OPERATING PROCEDURE String Inverter Installation – Zeverlution Series Version 1.2 Effective date 02/08/2017 SUNCLIX Connectors The inverter uses SMA’s SUNCLIX to connect the DC string to the inverter. One (Zeverlution 2000s), or two pairs (Zeverlution 4000) respectively, are shipped with the inverter. It is important to assemble the connectors correctly.
  • Page 9: Ts4-R-O Optimiser Installation

    STANDARD OPERATING PROCEDURE String Inverter Installation – Zeverlution Series Version 1.2 Effective date 02/08/2017 5. If the connector’s clamping bracket was locked prematurely (refer to step 3), it can be opened using a 3.5mm flat bladed screw driver Equipotential Bonding Equipotential bonding is required for all parts of the solar array.
  • Page 10: Ac Wiring

    STANDARD OPERATING PROCEDURE String Inverter Installation – Zeverlution Series Version 1.2 Effective date 02/08/2017 2. Connect the module leads to the short input leads of the TS4-R-O unit. 3. Connected the long output leads of the optimiser to the output leads of the next optimiser.
  • Page 11: System Commissioning

    STANDARD OPERATING PROCEDURE String Inverter Installation – Zeverlution Series Version 1.2 Effective date 02/08/2017 An AC isolator must be installed adjacent to the inverter if the inverter is more than 3 meters away from the switchboard or it is out of line of sight. The AC isolator must have a current rating equal to or greater than the MCB current rating.
  • Page 12: Connecting The Inverter To The Internet

    STANDARD OPERATING PROCEDURE String Inverter Installation – Zeverlution Series Version 1.2 Effective date 02/08/2017 2. Once the inverter has started, use the grey button next to the display to change the information shown on the display until the inverter name is displayed, e.g.
  • Page 13: Connecting The Inverter To The Internet Using Wifi

    STANDARD OPERATING PROCEDURE String Inverter Installation – Zeverlution Series Version 1.2 Effective date 02/08/2017 Ethernet cable directly to the router. Refer to Section 6.3.2 for connecting the inverter using Ethernet. 6.3.1 Connecting the inverter to the internet using WIFI Install the supplied WIFI antenna to the bottom of the inverter before setting up the WIFI connection.
  • Page 14 STANDARD OPERATING PROCEDURE String Inverter Installation – Zeverlution Series Version 1.2 Effective date 02/08/2017 5. Select the wireless menu and connect to the customer’s wireless network. 6. After approximately one minute the inverter should connect to the customers wifi network and the status indicator on the wireless page will show a green tick.
  • Page 15: Connecting The Inverter To The Internet Using Ethernet

    STANDARD OPERATING PROCEDURE String Inverter Installation – Zeverlution Series Version 1.2 Effective date 02/08/2017 6.3.2 Connecting the inverter to the internet using Ethernet To use this method the customers router must have DHCP enabled. Connect the Ethernet port on the...
  • Page 16 Commissioning Test Sheet Residential - String Inverter solarcity PV array commissioning sheet Address of installation COC Reference/Certificate ID Number Date of Testing Number of PV modules in string 1 Number of PV modules in string 2 (if applicable) Number of DC optimisers (if used) Continuity Earth continuity 1 –...

This manual is also suitable for:

Zeverlution 2000sZeverlution 4000

Table of Contents