4. Applications

The Solar Station is designed to pump clean, thin, non-aggressive and non-explosive liquids, not
containing solid particles, fibres or mineral oil. It is recommended to use a water & glycol solution
(maximum 50% glycol).
The Solar Station is for use in the collector circuit of solar thermal systems in compliance with the
technical data specified in these instructions. This Solar Station comes equipped with safety valve to
prevent over pressure within the system.
In heating systems, the pumped liquid should meet the requirement of accepted standard on water
quality in heating systems.
Warning
The pump must not be used for the transfer of flammable liquids such as diesel oil, petrol or
similar liquids.
The maximum operating system pressure is 1.0 MPa (10 bar)

5. Installation - Wall mounting

The kit must be installed by a competent heating installer
1. Remove the enclosure top.
2. Place the solar station with enclosure bottom against the wall on the existing pipe work.
3. Tighten the connections.
4. Mark the wall through the two securing holes of the enclosure bottom.
5. Remove the solar station with enclosure bottom from the wall.
6. Drill holes in the wall and insert the wall plugs provided.
7. Fix the enclosure bottom with solar station to the wall using the M10 x 120mm screws
and washers provided.
8. Tighten all connections.
The unit must be installed so that the pump shaft is in the horizontal position.

6. Pump head replacement

1. Remove the enclosure top.
2. Close the isolating valves above and below the pump.
3. Let the pressure relieve in the installation below the isolating valves.
4. Loosen the hexagon allen screws (x 4) on the pump head.
5. Remove the pump head.
6. Place the new pump head in place, taking into account the position of the terminal box.
7. Re-fit and tighten the hexagon allen screws (x 4) on the pump head.
8. Open the isolating valves and fill with water.