Figure 3-7 Opening the valve
Step 8 Check the end pressure gauge on the front of the cabinet. The pointer should be in the green
zone and the pressure reading should be greater than 1.6 MPa. Record the reading of the
pressure gauge. 8 hours later, observe the pressure gauge again. The pressure reading should
remain unchanged.
----End

3.2.2 Installing a SmartLi

3.2.2.1 Securing Installation

Procedure
Step 1 Determine the cabinet installation position. Draw mounting holes in the installation position
according to the drawings.