Page 1
OPERATING INSTRUCTIONS D-2009/09/00712-8-3 | Date: 08/2019 TSA1 H 70 MPa Type Breakaway coupling for hydrogen refuelling at car refuelling stations ® - We Engineer Hightech...
WEH QA management in writing� Violation of WEH operating instructions will result in a loss of warranty and in addition the WEH GmbH will accept no liability for consequential damage caused to persons or property�...
Product may not be used (i) as safety accessory or (ii) for vessels as defined by the Pressure Equipment Directive 2014/68/EU. Therefore, the ® application of this WEH Product must comply with the classification as pressure accessory for piping. The assessment with regard to a different classification can, however, be made on request.
Type TSA1 H 70 MPa Operating instructions Date: 08/2019 3 INSTALLATION TSA1 H 70 MPa Breakaway coupling body Eccentric actuator Filter (internal) Receptacle insert Mounting Guide tube Fixing elements Retaining brackets Data cable Definition ports Media inlet Media outlet TSA1 H 70 MPa incl.
Page 6
Spare Parts) depending on the thread size. Please contact us! 3�1�5 The assembly data indicated (tightening torques, assembly turns etc.) are max. values and only valid for components delivered by WEH. The customer is respon- sible to check if his counterparts withstand these max. values determined by WEH.
Type TSA1 H 70 MPa Operating instructions Date: 08/2019 3�2�2 Fix the mounting (Pos. 5) to the dispenser at the fixing bores (see figure below). Back-up ring The mounting must be fixed at a position that is able to withstand the forces arising in case of an accidental deployment.
Type TSA1 H 70 MPa Operating instructions Date: 08/2019 4 EXAMINATION AFTER SEPARATION In the event of accidental deployment, e.g. driving a vehicle from the dispenser with the nozzle remaining in the vehicle fuel port, the breakaway coupling will separate the connection between dispenser and filling hose sealing both ends.
7�5 Violation of WEH maintenance instructions specified in this document will result in a loss of warranty and in addition the WEH GmbH will accept no liability for consequential dama- ge caused to persons or property. Page 9...
Type TSA1 H 70 MPa Operating instructions Date: 08/2019 8 EXAMINATION OF LEAK RATE 8�1 Instructions for examination of leak rate 8�1�1 Gas detectors are not suitable to measure a technical leak rate due to the techni- cal requirements. Therefore a gas detector can only be used as indicator. For this reason the max.
Type TSA1 H 70 MPa Operating instructions Date: 08/2019 9 RECOMMISSIONING Please note: Ensure that both end connections are depressurized prior to reassembling the breakaway coupling after a separation or for maintenance work. If the system is still pressurized, the nozzle cannot be disconnected from the receptacle, nor can the receptacle insert be reassembled to the breakaway coupling.
Page 12
Type TSA1 H 70 MPa Operating instructions Date: 08/2019 9�3 Recommissioning Note the following when separation occurs or for maintenance work: Both end connections must be depressurized prior to reassembling the breakaway coupling. 9�3�1 Turn the eccentric actuator (pos. 2) by 180° the clamping jaws open. 9�3�2 Insert the receptacle insert (pos.
Need help?
Do you have a question about the TSA1 H2 70 MPa and is the answer not in the manual?
Questions and answers