Rc Test Menu - ABB SACE Emax Series Installation, Service And Maintenance Instructions

Low voltage air circuit-breakers
Table of Contents

Advertisement

16.6.2
Putting into service
The PR122/P LSIRc unit comes already configured.
However, when a PR122/P LSIG or PR123/P LSIG units are used, follow the directions below to update the unit:
1.
Disconnect all power supplies;
2.
Replace the rating plug with one supplied by SACE for Rc application;
3.
Install the toroid on the busbars as shown in the 1SDH000601R0001 document;
4.
Connect the toroid to the release as per the wiring diagram on page 153;
5.
Power the unit through PR030/B and proceed to installation according to the following path: settings, CB, earth protection, external toroid,
RC. Confirm the changes;
6.
Check that no failures are indicated;
7.
Set threshold and times of Rc protection;
8.
Conduct an Rc test, see par. 16.6.3; check for correct operation.
16.6.3

Rc test menu

The test page of Rc protection can be accessed by pressing the "iTest" key for 7 seconds, or else the Rc test page can be reached through
the following path: test; Rc (Idn). Rc test screen will be displayed; press the "iTest" key again to test.
A successful result will be proved by CB opening within the times previously set.
In the event of a fault related to the connections between toroid and protection unit, the wording:
displayed.
L2234
Model
L2778
Apparatus
Doc. No.
1SDH000460R0002
GText sensor, will be
Scale
Emax
Page No.
134/158

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents