ARC GUARD SYSTEM™ – T VOC-2 INSTALL ATION AND MAINTENANCE GUIDE
Mounting and connecting the Arc Monitor to the system
This is a summarize of the complete procedure in
mounting and connecting the Arc Monitor.
WARNING
Make sure that supply voltage is switched
off before mounting and connecting the Arc
Monitor!
To mount and connect the Arc Monitor do the following
steps:
1.
Mount and connect external HMI (option).
See: "Mounting the HMI" on page 20.
2.
Connect extensions X2, X3 (option).
See: "Connecting extension module (option)" on
page 24.
3.
Place and mount the optical detectors. This
installation guide contains examples for placing the
detectors and information how to mount.
See page 21, 22, 23.
4.
Connect optical detectors to the Arc Monitor and
extensions (option).
5.
Connect optical cables (option) from current
sensing units, CSU to lower right hand side of base
unit (X1:21-22). See: "Connecting CSU cable" on
page 24.
6.
Connect optical cable (option) to output for
additional Arc Monitor (X1:23)
Connect electrical connections. See: "Connecting
7.
electrical connections" on page 24.
8.
Configure the system by setting the DIP switches.
See: "4.2.5 Configurations" on page 29.
9.
Supply the system with power.
10.
Go through Start-Up sequence in Human Machine
Interface, HMI. See: "4.3.1 Start-Up Sequence" on
page 33.
11.
Controlling the detectors and the system.
See: "4.3.2 Controlling" on page 35.
Installation
WARNING
Make sure that supply voltage is switched off!
Mounting the HMI
There are three options to mount the HMI; On the the
panel separately from the Arc Monitor, inside of the panel
or both using a extended cable to an extra HMI.