Making the system operational

Observe the following during commissioning:
Prior to commissioning vent the heating system via
radiators and air vents.
Check, whether the hot gas baffle plates have been
correctly inserted.
3.3

Commissioning the control device

Please check in the documentation of the series 4000
control device, which you are using, how to commission
the control device.
3.4

Start up the burner

Proceed with the commissioning of the burner in
accordance with the installation and maintenance
instructions included with the burner.
Complete the commissioning report included in the
burner documentation.
You may raise the flue gas temperature, if you discover
during measurements for the commissioning report, that
the flue gas temperature is too low for the type of
chimney used (danger of condensation).
36
Fig. 49 Check the location of the hot gas baffle plates
We reserve the right to make any changes due to technical modifications.
Installation and maintenance instructions Logano GE315 • Issue 02/2006

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents