About Installation Drawings - Simrad EK80 Installation Manual

Scientific wide band echo sounder
Hide thumbs Also See for EK80:
Table of Contents

Advertisement

Simrad EK80
3
Install the EK80 system units.
Note that some EK80 system units may be commercial. Unless ordered specifically
these are not included in the delivery, and must be purchased locally.
4
Install the cables between the EK80 system units.
Observe the relevant cable plan, procedures, as well as the general requirements for
cabling.
5
Power up the EK80 for the first time, and set it to work.
Note
In order to set up the EK80 in a safe and correct manner, these procedures must be
complied to!
6
Connect the peripheral units.
7
Run a complete system test.
The tests are described in Setting to work chapter in this manual, as well as in the
Harbour Acceptance Test and the Sea Acceptance Test documents.
Further requirements
Fill in and sign the Installation Remarks form, and send it to Simrad's support department
as specified on the form.

About installation drawings

The installation shipyard must provide all necessary design and installation drawings, as
well as the relevant work standards and mounting procedures.
Note
If required, all documents provided by the shipyard for the physical installation of the EK80
must be approved by the vessel's national registry and corresponding maritime authority
and/or classification society. Such approval must be obtained before the installation can
begin. The shipowner and shipyard doing the installation are responsible for obtaining and
paying for such approval.
Kongsberg Maritime offers free advice for installation planning. Proposed arrangements
may be sent for commentary or suggestions. The following drawings should be submitted