Commissioning
► Find and fix the leak.
► Measure the CO
CO
level remains below 0.2%, no leak in the flue system:
2
► End emissions test mode
✔ The heat generator shuts down.
► Close the test ports. When doing so, ensure the caps are seated firmly!
6.9
Configuring the heat generator
Standard settings for heat generator on the control module.
► Set parameters
6.10
Finishing the commissioning process
► Document values in "System and operator's log".
► Complete commissioning report
56 | WOLF GmbH
level again.
2
(7.1 Parameter
list).
(12.1 Commissioning
report).