Instruction Manual Pow-R-Line Retrofit Panelboards Page Effective: November 2007 P1R & P2R Retrofit Panels Installation Criteria The Cutler-Hammer Pow-R-Line P1R & P2R panelboards are intended for use in the following list of panelboard enclosures and which meet the minimum size requirements listed in the table below.
The information or statements in this publication concerning the suitability, capacity or performance of the panelboard(s) may not cover all configurations of this custom built product. Eaton Electrical has “CAUTION” INDICATES A POTENTIALLY made all reasonable efforts to ensure that the...
Instruction Manual Pow-R-Line Retrofit Panelboards Page Effective: November 2007 P1R & P2R Retrofit Panels Removal of Existing Pre-Installation: Receiving, Panelboard Interior Handling and Storage DO NOT work on electrical equipment while energized. Verify power entering the equipment is de-energized at the source. Receiving Follow appropriate lockout procedure to this panel before starting work.
Page 5
Instruction Manual Pow-R-Line Retrofit Panelboards Page Effective: November 2007 P1R & P2R Retrofit Panels Fig. A Fig. C Locating Interior Mounting Holes in Loosen qty 8 10-32 screws Fig. D installed on the Enclosure chassis corners. In most instances the chassis should be centered in the enclosure unless a special offset trim has been ordered.
Page 6
Instruction Manual Pow-R-Line Retrofit Panelboards Page Effective: November 2007 P1R & P2R Retrofit Panels the full length of the lug body. Tighten lug, then torque to levels indicated on the panelboard label. Install Interior If compression lugs are utilized and supplied with the panelboard, the lugs will be mounted on the incoming lug pad.
Page 7
Remove all debris, if present. the National Electrical Code for specific requirement 6. Verify all field wire connections have or contact Eaton Electrical. Field-testing of ground the proper torque per instructions on the fault protection must follow instructions provided panelboard and on components.
Page 8
Pow-R-Line Retrofit Panelboards Page Effective: November 2007 P1R & P2R Retrofit Panels leaflets that are shipped with each panelboard containing GFP or contact Eaton Electrical. DISCONNECT POWER AT SOURCE BEFORE REMOVING OR INSTALLING FUSES. HAZARDOUS VOLTAGE. WILL CAUSE SEVERE Preparing Panelboard for INJURY OR DEATH.
Instruction Manual Pow-R-Line Retrofit Panelboards Page Effective: November 2007 P1R & P2R Retrofit Panels device. Inspection and test operations should be TO PREVENT DAMAGE TO GROUND FAULT coordinated with an overall testing program to result CONTROL CIRCUITS, METERING CIRCUITS, OR in the least operating inconvenience and system OTHER CONTROL CIRCUITS WHEN shutdowns.
Page 10
Instruction Manual Pow-R-Line Retrofit Panelboards Page Effective: November 2007 P1R & P2R Retrofit Panels Maintenance after Cleaning After cleaning, perform a second Megger or DC test of the panelboard insulation between phases and HAZARDOUS VOLTAGE. WILL CAUSE SEVERE ground. Prior to testing, remove all control power INJURY OR DEATH.
Page 11
Check all panelboard enclosure that could cause exposure to secondary wiring connections to ensure they are live parts. Contact Eaton Electrical for renewal parts properly connected to the panelboard ground bus, and assistance. After the physical damage has where indicated.
Page 12
Inspect for damage to components and any corrosion. If any damage or corrosion is present, contact Eaton Electrical. DO NOT RE-ENERGIZE PANELBOARD. After the panelboard has completely dried, remove all materials and tools from the equipment.
Need help?
Do you have a question about the Pow-R-Line P2R Series and is the answer not in the manual?
Questions and answers