Installation of Covering Roof
Horizontally Arranged Units
The roof slope for draining rainwater is created in the same way as with normal sloped roofs.
 The roof girders are combined according to the air-handling unit width and the required height (h1/h2) and spacing (B)
Figure 13
Covers for Overlapping Components
 Install the covers using 6.5 × 19mm roofing screws with rubber washers.
Figure 14
24
Air Handling Units
4M (1386mm)
5M (1692mm)
6M (1998mm)
7M (2304mm)
8M (2610mm)
9M (2916mm)
Figure 15
A
h1
h2
B
(mm)
(mm)
(mm)
-
150
677
-
150
830
-
150
983
150
200
757
150
200
859
150
200
961