Evaporator Mounting Preparation – Mushroom Installation
L
L
1
3
6
4
8
5
7
Measure the roof depth from the outside of the roof to the inside
of the inner box skin (distance "L").
Measure mushrooms from the bottom of the head
to end of the mushroom. Mark and cut them to the
same length "L". Apply waterproof silicone caulk to
the underside of the mushroom head and tap into
the vehicle roof to slightly crush the caulk. Bolt the
evaporator in place using the hardware supplied.
2
The correct bolting arrangement is show with the mushrooms
and evaporator in place. Note that the evaporator should not
press directly against the mushrooms due to the step drilling.
1) Mushroom (34-01262-00)
2) Silicone caulk
3) Vehicle roof
4) Box insulation
62-11165 Rev D
5) Inner box skin
6) Evaporator housing
7) Washer
8) Mounting screw
®