VII. Set-Up
Move the WOWMAKER to its intended position. This must be flat and able to support ~ 750kg, which corres-
ponds to a floor load of ~ 600kg/m².
ATTENTION: During transport, make sure that the Flightcase is not tilted sideways by more than 9 de-
grees. Installation at maximum angle of 3 degrees.
STEP 1: Once the WOWMAKER has reached its intended position, remove the rear part of the Flightcase
(wider one). To do so, open the ten butterfly locks. If necessary, the WOWMAKER can now be repositioned.
ATTENTION: At least two people are required to remove the case. Otherwise there is a risk of
accidents. Set the rear part of the case down carefully.
STEP 2: Open the butterfly locks on the front part of the case. Remove the front part of the case and set it
down carefully.