Provisions by others

Hoistway
o
The hoistway must be designed and built in accordance with all applicable codes (identified on the cover of
this manual) and all state and local codes.
o
Due to close running clearances, owner/agent must ensure that hoistway and pit (where provided) are level,
plumb and square and are in accordance with the dimensions on the installation (shop) drawings.
Minimum overhead clearance
o
Owner/agent must ensure minimum overhead clearance is in compliance with codes.
Construction site
o
Owner/agent to provide all masonry, carpentry and drywall work as required and shall patch and make good
(including finish painting) all areas where walls/floors may need to be cut, drilled or altered in any way to
permit the proper installation of the lift.
Dimensions
o
Contractor/customer to verify all dimensions and report any discrepancies to our office immediately.
Structural
o
Structural engineer to assure that building and shaft will safely support all loads imposed by the lift
equipment. Refer to the tables on installation (shop) drawings for loads imposed by the equipment.
o
Suitable lintels must be provided by owner/agent. Door frames are not designed to support overload wall
loads.
Entrances
o
Entrance assemblies must be adjusted to align with platform and interlock equipment. Others to allow an
adequate rough opening.
o
Return walls at entrances must be built-in by others after entrance assemblies are in place. Entrance assembly
must be securely fastened to walls by elevator contractor.
o
Fascia panel below upper level entrance where required. Fascia panel must be fastened to a solid wall and be
perpendicular to the floor and walls. Hoistway fascia is not self-supporting for long, continuous runs void of
entrances. Adequate support for the fascia must be provided.
Machine room
o
Machine room must be located at the lowest level adjacent to hoistway, unless shown otherwise on
installation (shop) drawings. Field adjustment by installer may be necessary to meet job site conditions or
regulations. Access to machine room to be through self-closing lockable door.
o
Sleeves for oil and electric lines must be provided from machine room to runway as required (positioned per
installer's instructions).
Electrical
o
Power supply with a lockable fused disconnect and auxiliary contact to break the battery feed, or circuit
breakers with a 3-pole breaker for battery feed required, in compliance with electrical code, located on the
wall on the lock jamb side of the machine room door. Contact your Savaria dealer or refer to one of the tables
on the next page for OEM part numbers.
o
Permanent power of 208 volts, three-phase, 30 amps or 230 volts, single-phase, 40 amps must be supplied by
others before installation begins.
o
Owner/agent to ensure at least 9.3 foot-candles (100 lux) ambient lighting over lift area.
o
Remote hall call (when supplied) to be installed by the owner/agent at 42" (1067 mm) from landing floor and
8" (203 mm) from the door edge.
Part No. 000783, 24-m09-2015
Infinity and Infinity HD Planning Guide
41
50-

Advertisement

Table of Contents
loading

This manual is also suitable for:

Infinity hd

Table of Contents