ETG LDO AC 3.0 Installation And Operation Manual page 12

Door drive
Table of Contents

Advertisement

6. Switch on the power supply.
The indicator of the converter displays „000", the PWR-LED and the Hz-LED light up.
7. Test of rotation direction of the generator:
With the self study of the rotation direction of the motor in regard of the door width
determination, the controller also recognizes the right rotation direction of the generator.
There is no need in changing the configuration of the channels A and B.
8. Check the DIP switch after supply: both switches must be placed in the "OFF" position.
If a centrally opening door is about to be driven, switch the DIP switch 1 in the "ON" position.
This causes standard parameters for centrally opening doors to be uploaded into the memory
during door width estimation.
off
Figure 4-2 DIP switch
9. Door width determination
-
In order to begin the door width determination, both mechanical end stops (rubber buffers
for "Door open" and "Door closed") must be set up.
-
To recognize the closing edge, the door has to be opened with a maximum of 5-10 cm. At
first the controller is searching the closing edge and after that the door will move to the
position "door open". Both positons will be stored.
Caution!
During every door width determination, every parameter values are overwritten with
standard parameter values! The changed parameter values should be noted down prior to
the operation.
Starting the door width evaluation:
Open the door not more than 5 – 10 cm, starting at the closing edge. Switch the DIP switch 2
to the „on" position and then press and hold the „Door closed" button (Figure 4-2/1) for over
3 seconds. The door starts moving then. The button may be released now.
The following functions are performed automatically. At first the door moves alternating to
the first stop if it is necessary. This stop the control defines as closing edge.
Finally, a slow opening motion is performed in order to evaluate the "Door open" position.
The estimated opening width is stored and is available also after a case of a power outage.
After a successful door width evaluation, the DIP switch 2 must be again switched into the
"off" position. Finally, the control moves to the "Door open" status.