StorEdge™ Inverter Wiring Guide & On Site Checklist for Europe, APAC, South Africa
This document is a battery wiring guide and contains an on-site checklist with steps for post-installation verification of a StorEdge system for the following batteries:
LG Chem RESU7H/RESU10H
For more details, please refer to the StorEdge Installation Guide supplied with the StorEdge Inverter. For additional assistance contact SolarEdge Support (see page 8).
Wiring Guide
WARNING!
For LG Chem RESU7H/RESU10H batteries:
Before wiring the system, make sure that the battery is powered off, using both of the following switches:
* Auxiliary power supply switch
* Circuit breaker switch
Figure 1: LG Chem Auxiliary Power Switch and Circuit Breaker Switches
Page 1
For LG Chem RESU7H/RESU10H batteries: Before wiring the system, make sure that the battery is powered off, using both of the following switches: * Auxiliary power supply switch * Circuit breaker switch Figure 1: LG Chem Auxiliary Power Switch and Circuit Breaker Switches...
StorEdge Inverter Wiring and On Site Checklist Wiring Types and Connectors To connect the battery to the StorEdge Inverter, use the following wiring types and connectors: LG Chem RESU7H/RESU10H Battery Recommended Cable Type (min-max cross section) SolarEdge Connector Connector DC: 6 mm (2.5-6 mm...
Page 3
B- <> B- and A+ <> A+ on the same twisted pair Figure 2: Connecting the LG Chem RESU7H/RESU10H to a StorEdge Inverter with Two DIP Switches and SolarEdge Meter Connecting the LG Chem RESU7H/RESU10H to a StorEdge Inverter with Three DIP Switches and SolarEdge Meter...
StorEdge Inverter Wiring and On Site Checklist Switch Settings Setting the DIP Switches on the Inverter Communication Board Set DIP switch SW7 RS485-1 RS485-2 For RS485-1 connections, use DIP Switch 1 (leftmost): For RS485-2 connections, use DIP Switch 2 (rightmost): * ON (up): Terminated (no meter installed) * ON (up): Terminated (no meter installed) * OFF (down): Not terminated (meter is installed)
Page 5
Check connection to the Internet with one of the following options: Ethernet, Wi-Fi, Cellular, ZigBee Module. The connection status displayed should be S_OK. Commissioning LG Chem Battery: Switch on Auxiliary power supply and Circuit breaker switch, as shown in Figure 1. ...
Page 6
StorEdge Inverter Wiring and On Site Checklist Verification Action Step Checked RS485 Configuration Verification (for one Battery and one Export + Import meter) If not already OFF, switch OFF the StorEdge Connection Unit switch (for StorEdge inverter). Switch the inverter ON/OFF switch to OFF. ...
Page 7
StorEdge Inverter Wiring and On Site Checklist Check Battery Connection Scroll through the menus until you reach the battery status screen. Check the battery information: BSN (battery serial number), ID (15 for LG), SOE (battery capacity in percentage), PWR (charge/discharge power), Total (total discharged energy) and the State (Charging/Discharging, Idle, Init or Fault).
StorEdge Inverter Wiring and On Site Checklist Support and Contact Information Australia (+61) 1800 465 567 support@solaredge.net.au APAC (Asia Pacific) (+972) 073 2403118 support-asia@solaredge.com China (+86) 21 6212 5536 support_china@solaredge.com France and Belgium (+33) 0800 917 410 support@solaredge.fr DACH and Rest of Europe (+49) 089 454 59730 support@solaredge.de Italy (+39)