Transport, storage and packing
Fig. 12
Removing screws from the pallet
Transporting without
brackets
12
Only lift the vacuum circuit-breaker so that all sling gear is tensioned.
Remove angle plate and bracket screws from the pallet.
Lift the vacuum circuit-breaker from the pallet.
Remove all screw connections from the brackets on the pole plate and the
terminals.
Remove angle plate below mechanism box.
Transport to installation site or leave suspended from crane for further
work steps.
Note
Keep partitions and accessory pack ready for the installation.