1MRS757641 E
4.3.3
620 series
Installation Manual
A
B
C
GUID-8A388D00-81BB-4C28-BC1B-D8C66F0C0E83 V1 EN
Figure 10:
Flush mounted case and plug-in unit
A
262.2 mm
B
177 mm
C 246 mm
D 201 mm
E
153 mm
F
48 mm
G 160 mm

Semi-flush mounting the IED

A mounting kit is needed for semi-flush mounting the IED. The mounting kit includes
screws, a raising frame and gasket.
To install a semi-flush, a panel cut-out of 248 x 162 mm with mounting holes and 103
mm depth behind the panel is required.
Section 4
Mounting
D
E
G
F
21