Section 4
Mounting
24
1.
Mount the mounting panel to a 19" rack.
2.
Loosen the four M5 fixing screws in the case to fit the case into the panel cut-out.
3.
Mount the case to the panel cut-out.
GUID-1D229768-569A-4597-9BE9-27C8FE1276DE V1 EN
Figure 14:
19" rack mounting panel, height 4U
4.
Tighten the screws.
The allowed range for the fixing screws' tightening torque is
0.7...1 Nm.
5.
Install the plug-in unit into the case.
There is a protective film on the top side of the IED. Its purpose is to prevent debris
falling inside the unit while installing electrical wiring. Remove the protective film
before energizing the IED.
1MRS757641 E