III-A. Included Components and Parts

The following items are included with your Swift-E load bank. If any of the following are not
included, please contact your Simplex representative at 800-637-8603.
1.
Swift-E load bank
2.
Manual

III-B. Primary Inspection

Preventative visual inspection of the shipping crate and the load bank is advised. Physical or
electrical problems due to handling and vibration may occur. Never apply power to a load
bank before performing this procedure. The following five-point inspection is recommended
before installation and as part of the 50-hour / 6-month maintenance schedule or as a load
bank is relocated:
1.
If the crate shows any signs of damage, examine the load bank in the corresponding
areas for signs of initial problems.
2.
Check the entire outside of the cabinet for any visual damage, which could cause
internal electrical or mechanical problems due to reduced clearance.
3.
Inspect all relays and control modules. Make sure all components are secure in their
bases and safety bails are in place. Spot check electrical connections for tightness. If any
loose connections are found, inspect and tighten all remaining connections.
4.
Examine all accessible internal electrical components such as fuses, contactors, and
relays. Check lugged wires at these components.
5.
Visually inspect the element chamber for foreign objects, broken ceramic insulators,
and mechanical damage.
Call Simplex if you have any problems during installation.
24-hour contact at 800-637-8603
III. UNPACKING
8 June 2018 • Simplex Service 800-637-8603 • Page 9 of 19
Swift-E / Swift-E+ Load Bank Manual

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the SWIFT-E+ and is the answer not in the manual?

This manual is also suitable for:

Swift-e

Table of Contents