V-I. Startup
Before operating the Swift-E load bank, ensure that the unit is wired properly based on
the instructions from
When wired appropriately, the unit is ready to apply a load to a power source. Set
1.
the Meter Range toggle switch to the appropriate input voltage (120V or 240V).
Turn on the power source.
2.
Flip the toggle switch to "On" for the Fan/Control selection. If the system is
3.
operating properly, you will hear the fans start and the meter will turn on.
V-II. Applying a Load
Flip the toggle switch under "Master" to "On." This will allow
1.
you to begin applying load to the source as each load step is
activated.
Activate each load step by switching the desired step on.
2.
This step, if done while the "Master" switch is activated, will
apply the load instantly. For example, while the "Master"
switch is activated, powering 250W then 500W will apply
750W. If you wish to conduct a block load test, turn the load
switches on before flipping the "Master" Switch.
Using the digital meter (see
3.
voltage, amps, and frequency (Hz) of the load. The meter will not display amperage
values at less than 4 amps.
V-III. Shutdown
When your operation has completed, switch the "Master" and other load toggle
1.
switches to "Off." This will remove the load from the unit. Allow the unit to run for
five minutes to cool down.
Flip the toggle switch for the "Fan/Control" selection to "Off."
2.
Turn off the power source
3.
Disconnect the load bank from the power source.
4.
The unit is now off and is ready to be moved.
5.
V. OPERATING INSTRUCTIONS
"Wiring the load bank" on page
"Figure 3 Meter" on page
8 June 2018 • Simplex Service 800-637-8603 • Page 12 of 19
Swift-E / Swift-E+ Load Bank Manual
10.
Figure 4: Applying a Load
11), you can monitor the