3 Configuration
3.2
Creating a PLC application
The following description requires that a setup project has been created and transferred to the
system in advance with the measuring, control, and automation system's setup program. The
system must now be extended to include an operating panel, which has been connected in ad-
vance, as described in the "Connection" chapter.
3.2.1
Starting CODESYS
CODESYS is started from the setup program.
Step
1
18
Activity
Setup program: Project > Project settings > PLC > Start CODESYS
Important:
- PLC application = Own PLC application
- With I/O mapping of the modules