If the inverter starts converting after the initial connection to the AC, the
inverter then goes into Standby mode until enough power is generated (the
inverter LED flickers green). While the inverter is in Standby mode, the
following message is displayed:
R e m a i n i n g :
During this time, the inverter monitors the grid and verifies correct grid
voltage and frequency. This message indicates how many seconds remain
until the inverter will be in Production mode. This amount of time is in
accordance with the regulations of each country, and is typically between
three to five minutes.
The inverter then automatically goes to Production mode and produces power
(the inverter LED is steady green).

Step 3, Verifying Proper Operation

After the proper wake-up delay time is over, the following message appears on
the inverter's LCD panel:
V a c [ v ]
2 3 0 . 7
P _ O K :
To verify proper operation:
1
Verify that the inverter LED is steady green.
2
Verify that the ON/OFF indicator on the LCD panel, described above, reads
ON.
3
Verify that P_OK appears to indicate a connection to the power optimizers.
Also, verify that S_OK appears, if the inverter is connected to the SolarEdge
Monitoring Server.
SolarEdge Installation Guide – MAN-01-00002-1.6
W a k i n g
V d c [ v ]
3 7 1 . 9
X X X / Y Y Y
Commissioning the Installation
U P . . .
0 5 1 S e c
P a c [ w ]
2 3 4 9 . 3
< S _ O K >
O N
60