Install Vertical Termination Cap; Install Decorative Wall Components; Heat Shield Requirements For Horizontal Termination - Heat & Glo SLR-D Owner's Manual

Vented gas fireplace heaters
Table of Contents

Advertisement

H. Install Vertical Termination Cap
• Attach the vertical termination cap by sliding the inner
collar of the cap into the inner flue of the pipe section
while placing the outer collar of the cap over the outer
flue of the pipe section.
• Secure the cap by driving three self-tapping screws
(supplied) through the pilot holes in the outer collar of
the cap into the outer flue of the pipe (see Figure 10.14).
Termination Cap
(1 of 3)
Screws
Caulk
Figure 10.14
I. Install Decorative Wall Components
A decorative wall thimble can be installed on wall through
which the vent passes. The decorative wall thimble is used
to cover the firestop.
• Slide the decorative wall thimble over the last section of
horizontal pipe before connecting the termination cap to
the pipe.
• Once the pipe section and the termination cap have been
connected, slide the wall thimble up to the interior wall
surface and attach with screws provided. See Figure
10.15.
Figure 10.15 Wall Thimble
J. Heat Shield Requirements for Horizontal
WARNING! Risk of Fire! To prevent overheating and fire,
heat shields must extend through the entire wall thick-
ness.
There are two sections of the heat shield. One section
is factory-attached to the wall shield firestop. The other
section is factory-attached to the cap. See Figure 10.16.
If the wall thickness does not allow the required 1-1/2 in.
(38 mm) heat shield overlap when installed, an extended
heat shield must be used.
• If the wall thickness is less than 4 in./102 mm (DVP)
• Use an extended heat shield if the finished wall thickness
Storm
Collar
• The extended heat shield may need to be cut to length
• Attach the extended heat shield to either of the existing
• Rest the small leg on the extended heat shield on top
Heat & Glo • SLR-D • 2333-900 Rev. F • 9/17
Termination
• DO NOT remove the heat shields attached to the
wall shield firestop and the horizontal termination cap
(shown in Figure 10.16).
• Heat shields must overlap 1-1/2 in. (38 mm) mini-
mum.
or 4-3/8 in./ 111 mm (SLP), the heat shields on the cap
and wall shield firestop must be trimmed. A minimum
1-1/2 in. (38 mm) overlap MUST be maintained.
is greater than 7-1/4 in. (184 mm).
maintaining sufficient length for a 1-1/2 in. (38 mm)
overlap between heat shields.
heat shields using the screws supplied with the extended
heat shield. Refer to vent components diagrams in the
back of this manual.
of the pipe section to properly space it from the pipe
section.
Important Notice: Heat shields may not be field constructed.