5. Verify that the inverter is configured to the proper country: Press the LCD light button until reaching
the ID status screen:
I D :
# # # # # # # #
D S P 1 / 2 : 1 . 0 2 1 0 / 1 . 0 0 3 4
C P U : 0 0 0 3 . 1 9 x x
C o u n t r y : U S A 1
6. If required, perform the following additional steps before closing the inverter cover:
Country settings or inverter configuration using the internal LCD user buttons – refer to
l
Country and Grid on page 60.
Communication options connection – refer to Setting Up Communication to the Monitoring
l
Platform on page 72.
StorEdge application configuration - refer to System Configuration on page 81.
l
7. Close the inverter cover b y tightening the screws with a torque of 9.0 N*m/ 6.6 lb*ft. For proper
sealing, first tighten the corner screws and then the two central screws. The following figure
illustrates recommended order:
8. Close the Connection Unit internal cover: Attach the cover and secure it by tightening the four
screws with a torque of 1.2 N*m / 0.9 ft.*lb.
9. Make sure the AC Bypass switch in the Connection Unit is switched to the left (position 1).
10. Make sure the backed-up loads AC breaker i n the Connection Unit is UP.
SolarEdge-StorEdge Installation Guide MAN-01-00262-1.3
# #
Figure 29: Tightening order of the screws
Figure 30: Connection Unit
Chapter 7: Commissioning the Installation
47