Do not work with electrical current or work in elevated or exposed locations during a thunderstorm. Anti-corrosion measures are required if an RTN 360 is installed in a location that is prone to corrosion. Contact the local Huawei office for details. A location is prone to corrosion if it is: Extreme weather conditions •Within 3.7 km of an ocean or a salt water lake...
Page 3
Inside the maintenance compartment RSSI/NMS port • The recommended USB flash drive is a 4 GB Netac U208. If a different model or capacity is required, contact the local Huawei USB port office. USB flash drives not meeting requirements may be incompatible.
Page 4
Terminating an Outdoor Network Cable with Shielded RJ45 Connectors Prepare an outdoor network cable Arrange the core wires according to the pin assignments and cut them Prepare the following tools. Strip the cable. and shielded RJ45 connectors. neatly (exposing a length of 12 mm). 8: brown 7: white and brown 6: green...
Page 5
Installing an RTN 360 Installing an RTN 360 at the Edge of a Mobile Backhaul Network Installation procedure Install an RTN 360 on a pole or wall. RTN 360 Install the ground cable. Connect one end of an outdoor network cable to port P&E on the RTN 360.
Page 6
Installing an RTN 360 Installing RTN 360s at 2x(1+0) Aggregation Sites Installation procedure Install two RTN 360s on a pole or wall. Install their respective ground cables. RTN 360 Connect an outdoor network cable to port P&E on each RTN 360. Optional: Install the RTN 360 on a pole.
Page 7
References for Installation Optional: Installing an RTN 360 on a Pole Pass the hose clamps through the fastener and fix the hose Install the RTN 360 box securely on the fastener. clamps on a pole using the screws of the hose clamps. Before fixing the hose clamps, ensure that the azimuth faces the peer site.
References for Installation Installing Cables Install a ground cable. Ensure that the OT terminal of the Install an outdoor network cable. ground cable is correctly installed. 1. Unscrew the PG cover installed on port P&E of the RTN 360 using a 1.8 N•m torque wrench (rotating the wrench counterclockwise).
Page 9
References for Installation Aligning an RTN 360 Adjust the azimuth and elevation of the RTN 360 by rotating the azimuth and Install the alignment scope. Eyepiece Lens elevation adjustment nuts. Holes for installing the alignment scope By rotating azimuth adjustment nut (nut 1), you can adjust the azimuth of the RTN 360 from -50°...
Page 10
References for Installation Powering On an RTN 360 •After unpacking an RTN 360, power it on within 24 hours. •Ensure that the Dock is powered on and works properly. •Do not power off an RTN 360 for more than 24 hours during maintenance. •On an RTN 360, only port P&E supports power over Ethernet.
References for Installation Loading Configuration Data and Measuring the RSL Load configuration data. Measure the RSL. USB flash drive Close the maintenance compartment. Open the maintenance compartment. RSL tester Web LCT If a Wi-Fi module is installed at the USB port, you can determine whether the Wi-Fi module is working properly by enabling it to search for the SSID of an NE in the wireless LAN.