Recording; Secondary Injection; Alarm Test; Self Supervision Check - ABB RELION REC650 Commissioning Manual

650 series bay control version 2.2
Hide thumbs Also See for RELION REC650:
Table of Contents

Advertisement

1MRK 511 425-UEN A
10.2.2.2
10.2.2.3
10.2.2.4
10.2.2.5
10.2.2.6
Bay control REC650 2.2 IEC
Commissioning manual
Commissioning and maintenance of the fault clearing system
Test instructions for protection IEDs to be tested
Test records from previous commissioning and maintenance tests
List of valid settings
Blank test records to fill in measured values

Recording

It is of utmost importance to carefully record the test results. Special test sheets
covering the frequency of test, date of test and achieved test values should be used.
IED setting list and protocols from previous tests should be available and all results
should be compared for differences. At component failures, spare equipment is
used and set to the requested value. A note of the exchange is made and the new
measured values are recorded. Test records for several years of testing should be
stored in a common file for a station, or a part of a station, to give a simple
overview of the period of testing and achieved test values. These test records are
valuable when analysis of service disturbances shall be done.

Secondary injection

The periodic maintenance test is done by secondary injection from a portable test
set. Each protection shall be tested according to the secondary injection test
information for the specific protection IED. Only the setting values adopted shall
be checked for each protection function. If the discrepancy between obtained value
and requested set value is too big the setting should be adjusted, the new value
recorded and a note should be made in the test record.

Alarm test

When inserting the test handle the alarm and event signalling is normally blocked.
This is done in the IED by setting the event reporting to Off during the test. This
can be done when the test handle is inserted or the IED is set to test mode from the
local HMI. At the end of the secondary injection test it should be checked that the
event and alarm signalling is correct by activating the events and performing some
selected tests.

Self supervision check

Once secondary testing has been completed, it should be checked that no self-
supervision signals are activated continuously or sporadically. Especially check the
time synchronization system and communication signals.

Trip circuit check

When the protection IED undergoes an operational check, a tripping pulse is
normally obtained on one or more of the output contacts and preferably on the test
switch. The healthy circuit is of utmost importance for the protection operation. If
the circuit is not provided with a continuous trip-circuit supervision, it is possible
Section 10
SEMOD56528-14 v2
SEMOD56528-17 v2
SEMOD56528-20 v4
SEMOD56528-23 v5
SEMOD56528-26 v5
101