Restoring - ABB RELION REC650 Commissioning Manual

650 series bay control version 2.2
Hide thumbs Also See for RELION REC650:
Table of Contents

Advertisement

1MRK 511 425-UEN A
10.2.2.8
Bay control REC650 2.2 IEC
Commissioning manual
Commissioning and maintenance of the fault clearing system

Restoring

Maintenance is very important to improve the availability of the protection system
by detecting failures before the protection is required to operate. There is however
little point in testing healthy equipment and then putting it back into service with
an open terminal, with a removed fuse or open miniature circuit breaker with an
open connection, wrong setting, and so on.
Thus a list should be prepared of all items disturbed during test so that all can be
put back into service quickly and without overlooking something. It should be put
back into service item by item and signed by the responsible engineer.
Section 10
SEMOD56528-36 v2
103