1.
Check that AutoLock and TripLockout are both set to Disabled.
2.
Initiate a three-phase fault.
The functional output TRIP should be active at each fault. The output CLLKOUT
must not be activated.
3.
Activate the automatic lockout function, set AutoLock = Enabled and repeat.
Besides the TRIP outputs, CLLKOUT should be set.
4.
Reset the lockout signal by activating the reset lockout (RSTLKOUT) signal.
5.
Activate the TRIP signal lockout function, set TripLockout = Enable and repeat.
The output TRIP must be active and stay active after each fault. CLLKOUT must be
activated.
6.
Reset the lockout.
All functional outputs should reset.
7.
Deactivate the TRIP signal lockout function, set TripLockout = Disabled and the
automatic lockout function, set AutoLock = Disabled if not used.

Completing the test

Continue to test another function or end the testing by setting the parameter TestMode to
Disabled under Main menu/Tests/IED test mode/TESTMODE:1. If another function is
tested, then set the parameter Blocked to No under Main menu/Tests/Function test
modes/Logic/SMPPTRC(94,1->0)/SMPPTRC:X for the function, or for each
individual function in a chain, to be tested next. Remember to set the parameter Blocked to
Yes, for each individual function that has been tested.

Tripping logic phase segregated output SPTPTRC (94)

Prepare the IED for verification of settings as outlined in
settings".
Values of the logical signals for SPTPTRC (94) are available on the local HMI under
Main menu/Tests/Function status/Logic/SPTPTRC(94,1->0)/SPTPTRC:X. The
Signal Monitoring in PCM600 shows the same signals that are available on the local HMI.
This function is functionality tested together with other protection functions (ground-fault
overcurrent protection, and so on) within the IED. It is recommended that the function is
tested together with the autorecloser function, or when a separate external unit is used for
reclosing purposes. The testing is preferable done in conjunction with the protection
system and autorecloser function.

1p/3p operating mode

In addition to various other tests, the following tests should be performed. They depend on
the complete configuration of an IED.
Section 6
Testing functionality
5.1 "Preparing the IED to verify