4.3 Mount Drive Rail

B&B ARMR
A Division of B&B Roadway and Security Solutions
1. Place gate operator on the pad and
measure 3" from the face of a
vertical gate member to center of
the wheels.
2. With the drive wheels disengaged,
slide the drive rail between the
wheels, to the closed position.
3. Align the drive rail with a clearance
of 12.375 inches from the base of
the operator to the center of the
drive rail. Attach drive rail to the
vertical member closest to the
operator. Slide gate open and repeat
for each vertical member.
4. Close the gate. With the drive
wheels disengaged, slide the drive
rail between the open and closed
limit and verify that the drive rail is
level. Also verify that the drive rail
is equidistant from the drive wheels.
0054-9001UL Revision A2
15