Commissioning - gledhill BM125 Installation And Servicing Instructions

Boilermate 2000
Table of Contents

Advertisement

Open the incoming stop valve and fi ll the domestic mains cold and hot water
systems.
Fill the whole of the primary heating system with potable water through the
feed and expansion cistern.
Check the water level in the feed and expansion cistern and adjust the ballvalve
if necessary.
Check the whole of the primary heating and domestic hot and cold distribution
systems for leaks.
It is essential that all systems function properly for optimum performance.
To achieve this, the primary system should be commissioned in accordance with
good practice and generally in accordance with the requirements of BS 6798,
BS 5449 and BS 7593.
Full details of the requirements are given in PAS 33:1999 under Section 10

Commissioning.

Model
BM125
BM145
BM185
BM210
BM225
Model
BM125
BM145
BM185
BM210
BM225
Volume to be added to the system (litres)
Corrosion inhibitor agent
Sentinel X100
Fernox MB1
2
Volume to be added to the system (litres)
Cleansing agent
Sentinel X300
Fernox Superfl oc
2
2.0 INSTALLATION
2.3 COMMISSIONING
When using either cleansing or corrosion
inhibitor chemical, the manufacturers
instructions must be followed.
Cleansing the Primary System
When determining the quantity of cleanser
required, be sure to allow for the increased
volume of water in the primary circuit due
to the thermal store.
In most cases the quantities shown opposite
will be adequate for a typical 3/4 bedroom
property.
Primary Water System Treatment
Although the BoilerMate 2000 has no special
water treatment requirements, the radiators
and other parts of the circuit will benefit
from the application of a scale and corrosion
inhibitor such as Sentinel X100 or a Protector
such as Fernox MB1.
When determining the quantity of inhibitor
required, be sure to allow for the increased
volume of water in the primary circuit due to
the thermal store - see section 1.2 Technical
Data for volumes.
2
In most cases the quantities shown opposite
will be suitable for a typical 3/4 bed property.
POWERFLUSHING/CLEANING OF THE HEATING
SYSTEM
If it is proposed to 'powerfl ush' the heating
system we would recommend that the
BoilerMate appliance is isolated from the
heating system being cleaned. Failure to do
this could seriously damage the appliance.
When carrying out the work always comply
fully with the manufacturers instructions for
the powerfl ushing equipment being used.
2
If in any doubt please consult our Technical
Helpline.
Page 27