VC4E & VC6E Series Full Size Electric Convection Ovens - REMOVAL AND REPLACEMENT OF PARTS
Fig. 16
10. Reconnect lead wires at the motor, replace
conduit and junction box cover.
NOTE: Check data plate on motor for wiring
schematic. The motor must rotate clockwise when
viewed from the shaft end.
Fig. 17
11. Slide blower onto motor shaft until hub is flush
with end of shaft then tighten set screws.
12. Adjust motor position until blower is parallel to
motor mounting plate as outlined under
BLOWER ADJUSTMENT in SERVICE
PROCEDURES AND ADJUSTMENTS.
13. Position motor mounting plate on the rear wall
and secure with nuts and washers.
14. Replace the baffle panel.
15. Remove cardboard from the bottom of the oven
cavity.
16. Check oven for proper operation then replace
rack guides and racks
1.
Remove the top front cover as outlined under
COVERS AND PANELS.
2.
Disconnect the lead wires to the door switch.
3.
Remove the switch.
4.
Reverse procedure to install the replacement
switch and check for proper adjustment as
outlined under DOOR SWITCH ADJUSTMENT
in SERVICE PROCEDURES AND
ADJUSTMENTS.
1.
Remove the screws at the top and bottom of
door.
Page 13 of 64
DOOR SWITCH
Disconnect the
electrical power to the machine and
follow lockout / tagout procedures.
There may be multiple circuits. Be sure
all circuits are disconnected.
Fig. 18
DOOR WINDOW
Disconnect the
electrical power to the machine and
follow lockout / tagout procedures.
There may be multiple circuits. Be sure
all circuits are disconnected.
F25105 Rev. B (0217)