Commissioning - Potterton Paramount four Installation Manual

30-115 kw
Table of Contents

Advertisement

7 Commissioning

7
Commissioning
7.1
General
7.2
Checklist for commissioning
Tab.13 Checklist for commissioning
1.
System location
2.
Customer
3.
Boiler type/Designa­
tion
4.
Serial number
5.
Characteristic gas val­
ues
6.
7.
Have all pipelines and connections been checked for tightness?
8.
Flue gas system checked?
9.
Gas pipeline checked and vented?
10. Static pressure measured at the gas valve inlet?
11. Free wheeling of pumps checked?
12. Filling the heating plant
13. Water additives used
14. Gas flow pressure measured at full load at the gas valve inlet?
15. Gas injector pressure measured at full load at the gas valve outlet?
16. CO
content at low load
2
17. CO content at low load
18. CO
content at full load
2
19. CO content at full load
20.
Function test:
21.
22.
23.
24.
Programming:
25.
26.
27. Tightness of the flue system checked in operation (e.g. CO
28. Customer instructed?
29. Documents handed over?
44
Paramount four 30 – 115 kW
Wobbe index
Operating heating value
Heating mode
Domestic water mode
Time /date
Comfort setpoint heating circuit 1/2
Setpoint DHW
Automatic day time programme
Heating curve checked?
Danger
Commissioning may only be carried out by an approved installer.
The installer checks the tightness of pipes, the correct function of
all regulating, control and safety equipment, and measures the
combustion values. If this work is not carried out correctly, there is
a risk of considerable damage to persons, environment and prop­
erty.
test in annular gap)?
2
kWh/m³
kWh/m³
mbar
mbar
mbar
%
ppm
%
ppm
°C
°C
Clock
7658013 - 02 - 15092016

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents