06. INSTALLING AND STARTING THE MACHINE
06.4 AIR FLOW CLEARANCE (picture 5)
Maintain at least 1 metre of unrestricted space on all sides
of the unit. The service life and operating efficiency of the
power generator is reduced when the unit is subjected to
high levels of dust, moisture, and corrosive vapours.
Do not place any additional filtering device
over the air intake and air outlet.
Keep clean the area surrounding the air
intake and outlet screen.
Operate in well ventilated environment,
worrying himself that the gases of unloading
don't stagnate in the environment of job;
tender the unit away from walls or other
obstacles to avoid recycles of air or of gas
that they would provoke the overheating of
it. In the case you had to be operated in local
closed, to use some aspirators to guarantee
a correct exchange of air.

06.5 CHECKING MACHINE OPERATION

Perform a test of operation according to the instructions
included in the following Chapter

06.6 RUN-IN

The application of heavy loads to a new engine has the
effect of shortening the engine life. During the first 20 hours
of operation, and to allow for a good engine run-in, do not
use more than 70% of the maximum power output rated in
the technical specifications.
After first 50 hours of operation change the engine oil.
MPM 6/230 S-L
28
MI-M-00006200
pic.5