Unit Hanging
Confirm the pitch of the hanging rod is 790.0mm X 620.5mm (MCK-A) / 600.0mm x 582.0 mm
(MCK-B)/ 538.0 mm x 448.0 mm (MCK-C).
Hold the unit and hang it on the hanging rod with the nut and washer.
Adjust the unit height to 35.0 mm ( MCK-A/B) / 30.0mm (MCK-C) between the indoor unit bottom
surface and the ceiling surface.
Confirm with a level gauge that the unit is installed horizontally and tighten the nut and bolt to
prevent unit falling and vibration.
Open the ceiling board along the outer edge of the paper installation template.

Drain Piping Work

Drain Test
Note: This indoor unit use drain pump for condensed water drainage. Installed
the unit horizontally to prevent water leakage or condensation around
the air outlet.
Indoor Unit
3
MCK-A/B/C
• Drain pipe must be downward gradient for smooth
drainage.
• Avoid the drain pipe from up and down slope to prevent
reversal flow.
• During the drain piping connection, be careful not to exert
extra force on the drain connector at indoor unit.
• The outside diameter of the drain connection at the
flexible drain hose is 20 mm.
• Be sure to provide heat insulation (polyethylene foam
with thickness more than 8.0 mm) on the drain piping to
avoid the condensed water dripping inside the room.
• Connect the main drain pipe to the flexible drain hose.
• Feed water from flexible drain hose and check the piping
for leakage.
• When the test is completed, connect the flexible drain
hose to the drain connector on the indoor unit.