Combustion Chamber - Worcester Greenstar Heatslave II ErP 12/18 Installation, Commissioning And Servicing Instruction Manual

Floor standing oil-fired condensing combination boiler using conventional and room sealed flue
Table of Contents

Advertisement

Installation
The boiler is not designed to take the weight of the flue
system, this must be supported externally to the boiler.
▶ All horizontal flue sections must rise by at least 52mm for each metre
(3°) away from the boiler to ensure that condensate flows back into
the boiler for safe discharge via the condensate waste pipe.
▶ The horizontal terminal must be installed at 3° to ensure that the
condensate drains back to the boiler whilst also preventing rain
ingress down the air duct.
Bracket (M)
Screw (N)
Fig. 31
▶ The retaining bracket [M] must be fitted if a flue elbow is used on the
boiler flue outlet.
5.5

Combustion chamber

▶ Unscrew screws [G] and remove flue manifold access cover [H].
▶ Check that all the baffles [J] and baffle retainer [K] are correctly
fitted to the secondary heat exchanger.
▶ Remove the retaining nuts and washers [B].
▶ Remove combustion chamber/baffle access door [A].
K
J
G
H
G
G
G
12/18 kW Baffle
A
18/25 & 25/32 kW Baffle
B
Fig. 32
24
Bracket (M)
Screw (N)
G
G
C
6720805209-86.1Wo
▶ Ensure one piece baffle set [C] is in the right location [D], correctly
resting on the baffle rests [F] on either side of the combustion
chamber and pushed securely into place.
D
Fig. 33
▶ Refit combustion chamber door [A].
Secure with nuts and washers [B] and tighten until the
chamber door is firmly secured, do not over tighten the
nuts.
Greenstar Heatslave II
F
ErP -
6 720 813 344 (2014/09)