Direct Vent, Optional Horizontal And Vertical Vent Kits; Screen Installation - Westinghouse WBRC**140F Manual

Gas fired residential combi boiler installation / start-up maintenance / parts warranty
Table of Contents

Advertisement

24

2. Direct Vent, Optional Horizontal and Vertical Vent Kits

Figure 11 – Direct Vent, Vent Terminations (With Optional Kits)
All vent pipes must be glued, properly supported, and the exhaust must be pitched a minimum of ¼" per foot back to the appliance to
allow drainage of condensate. When placing support brackets on vent piping, the first bracket must be within 1 foot of the appliance and
the balance at 4 foot intervals on the vent pipe. Appliance venting must be readily accessible for visual inspection for the first three feet
from the appliance.

3. Screen Installation

After connecting the intake air and exhaust vent pipes, it is required to install the
included screens into the exhaust vent and intake pipe terminations to prevent damages
to the unit due to blockages. Clean the vent terminations and cement the screens into
the terminations. See Figure 12 for installation detail.
Figure 12 - Screen Installation
SAFETY INSTRUCTIONS
Do not connect any other appliance vents to the appliance exhaust vent or intake pipes.
WHL-015 REV. 5.20.16