6.2
BOX INSTALLATION PROCEDURE
6.2.1 Dig a hole big enough to hold the box
containing the operator (see F1)
6.2.2 Insert the tubes for water drainage in the
prepared holes (F1C)
6.2.3 Insert the sheath for laying the power
cables and limit switch (F1D).
Note: while positioning the box, keep in mind
the minimum distance there must be between
the pillar and the centre of rotation of the gate
hinge. (see F2)
Cement so that the box cannot be moved,
wait for it to dry and then assemble the
operator and levers.
Distance between Pillar - Hinge Centre
Distance between
Pillar - Hinge Centre
8