CONSIDERATIONS FOR INSTALLATION

· The installation and testing operations must be performed solely by qualified personnel in order
to guarantee the proper and safe operation of the automatic gate.
· The company declines any responsibility for damage caused by incorrect installations due to
incompetence and/or negligence.
· Before assembling the automatism, check that the gate is in perfect working order, hangs well
on its hinges and is suitably lubricated. It must also comply with the safety standards in force
in the country of installation..
1. Before fastening the brackets provided, establish the coordinates using the data given in
Table 1, bearing in mind that they are valid if the operator is at maximum extension minus one
centimetre of the available stroke (CD) when the gate is closed to obtain maximum working
efficiency.
2. Data B in the table, with reference to the single values A, are to be considered as values
(recommended).
3. To anchor the piston, use the fastening brackets provided.
COORDINATES AND TABLE
1. Establish coordinates A + B that are
to be used.
2. Note: The stroke used (CU) of the
operator must never be equal or
greater than the available stroke (CD)
3. The sum of coordinates A + B,
establishes the stroke used CU .
TABLE 1
Opening
A
angle
80
90
90
100
100
110
100
120
120
130
110
140
150
Note1: A+B = CU (Stroke used)

INSTALLATION

B
Cu
80
160
90
180
100
200
150
250
110
220
120
240
100
220
130
260
140
280
150
300
CD = (Available stroke) = 300/400/500 mm
Opening
A
angle
160
90°
175
Available
stroke =
190
400mm
200
90°
Available
250
stroke =
500mm
B
Cu
160
320
175
350
190
380
200
400
250
500