Optional Equipment
CONNECTING THE ELECTRICAL
POWER
See table below for current
ratings and wire sizes.
Service Entrance for
Three-Phase Power Supply
K
Electric – 4 wire with Ground
VOLTAGE
208V
240V
480V
600V
5–4
The steam boiler requires a separate three-phase electrical service for the
heating circuit. The sterilizer provides the 115 Vac required for the boiler
control circuits. Refer to the roughing-in drawing (Figure 6–1 on page 6–2)
for electrical specifications.
To connect the three-phase electrical supply to the steam boiler:
1. Remove the access cover from the steam boiler cabinet.
2. Refer to Figure 5–2 (GTS-30A) or Figure 5–3 on page 5–5 (CAS-45A).
Connect L1, L2, and L3 to the three-phase terminal. Torque the
terminals to 110 in-lbs.
3. Connect the ground wire to the ground terminal. The ground terminal is
located adjacent to the three-phase terminal.
FIGURE 5–2. GTS-30A STEAM BOILER ELECTRICAL CONNECTIONS
CURRENT
POWER
83.3 A
30 KW
72.2 A
30 KW
36.1 A
30 KW
28.8 A
30 KW
Be sure wires are clean and bright to
ensure good electrical contact.
Three-Phase Customer
Supply Connection
(torque to 110 in-lbs)
K
ELECTRICAL CABINET
(Cover Removed)
WIRE SIZE
CONDUIT
(90°C Copper)
SIZE
3 AWG
1¼"
4 AWG
1"
8 AWG
¾"
10 AWG
¾"