Powering The System On And Off; Power-On Self-Test - IBM eserver pSeries 7311 D10 Service Manual

Hide thumbs Also See for eserver pSeries 7311 D10:
Table of Contents

Advertisement

Powering the System On and Off

Power for the I/O subsystems is controlled by the attached processor subsystem and
the System Power Control Network (SPCN).

Power-On Self-Test

After power is turned on and before the operating system is loaded, the system does a
power-on self-test (POST). The RIO loop that connects the I/O subsystems to the
system unit is tested. Tests are also performed on the installed adapters and devices in
the I/O subsystems. If an error occurs during the POST, an error code is displayed on
the system operator panel LCD that indicates which part is failing and which subsystem
contains the error.
Eserver pSeries 7311 Model D10 and Model D20 Service Guide
36

Advertisement

Table of Contents
loading

This manual is also suitable for:

Pseries 7311 d20

Table of Contents