2. Power off the system and make sure all cables and connectors are disconnected
and are not dangling around the frame. The frame should be free to roll.
3. The floor eyebolts should be already secured to the concrete floor. Verify the
height of the center of the floor eyebolt to the concrete floor or the steel
beam/channel adapter mounted to the concrete floor. Ensure that the turnbuckles
can accommodate the total height of the raised floor.
4. Remove the floor tiles around the area where the frame(s) will be installed.
62
pSeries 690 Installation Guide
654.8 mm
(8) 49.3 mm
Eyebolt
64.6 mm
600 mm (23.6 Inch Floor) Tile Layout
(4X) Opening for Cables
64.6 mm
600 mm REF
(4X) 450 mm REF
23.6 in REF
654.8 mm