18.

OPERATION AND SERVICE

OPERATION:
Before operating the boiler, the entire system must be filled with water, purged of air and checked for
leaks. Do not use Stop leak or other boiler compounds. The gas piping must also be leak tested.
Any safety devices including low water cutoff, flow switch and high limit used in with this boiler must
receive periodic inspection (every six months) to assure proper operation. A low water cutoff of the float
type should be flushed every six months. All relief valves should be inspected and manually operated
every six months.
For your safety follow the lighting and operating instructions below and on the boiler.
To turn on main burner, slowly open firing valve after pilot is established.
Set primary system controller to desired temperature.
To turn off boiler close main manual gas valve, close pilot manual valve and turn off electric power to
system.
33